WHOLE HOUSE AUTOMATIC TRANSFER SWITCH - ALL aXis CONTROLLER
INSTALLATION
Wiring the ATS
US ATS model shown for reference. For Canadian installation,
refer to ATS Installation Manual.
The aXis ATS controls the automatic startup and shutdown
of the aXis HSB using Power Line Communication (PLC).
The PLC system utilizes the L1 and L2 power wires that run
between the ATS and HSB for communication. As a result,
there are no wires that need to be run between the ATS
and HSB besides the power wires (L1, L2, N, G) and battery
charger wires mentioned in this manual.
1. Have authorized utility personnel pull the utility meter from
the meter socket.
2. Remove door and dead front of ATS.
3. Connect Utility (L1-L2) to ATS Utility side breaker. Torque to
275 in-lbs.
4. Connect Utility N to Neutral lug. Torque to 275 in-lbs.
5. Connect earth GROUND to GROUND bar. NOTE: GROUND and
NEUTRAL bonded in this panel.
NOTICE
NOTICE
MODELS
®
6. Connect Generator L1-L2 to Generator side breaker. Torque to
45-50 in-lbs.
7. Connect Generator Neutral to neutral bar. Torque to
275 in-lbs.
8. Connect Generator Ground to ground bar.
Torque to 35-45 in-lbs.
9. Connect Load bars L1 and L2 to distribution panel.
Torque to 275 in-lbs.
10. Pull NEUTRAL from ATS to distribution panel. Pull GROUND
from ATS to distribution panel.
Remove bond from distribution panel if installed.
9
INSTALLATION
CAUTION