Validity: Floor installation
Condition: Version without drain pipework
Install the supplied condensate discharge tundish (3).
Slide the heating wire (1) from inside through the con-
densate discharge tundish and into the downpipe.
Adjust the internal heating wire in such a way that the
loop (4) lies concentric to the hole in the floor plate.
Ensure that the condensate discharge tundish is posi-
tioned in the centre above the downpipe in the gravel
bed.
Condition: Version with drain pipework
Install this design only in regions without ground frost.
Install the supplied condensate discharge tundish (3)
and adapter (2).
Connect the drain pipework to the adapter.
Slide the heating wire (1) from inside through the con-
densate discharge tundish and the adapter and into
the drain pipework.
Adjust the internal heating wire in such a way that the
loop (4) lies concentric to the hole in the floor plate.
Validity: Wall-mounting
Condition: Version without drain pipework
Install the supplied condensate discharge tundish (3).
Slide the heating wire (1) from inside through the con-
densate discharge tundish and to the outside.
Slide the end of the heating wire from the outside
through the condensate discharge tundish and back
to the inside until it forms a U-shape within the con-
densate discharge tundish.
Adjust the internal heating wire in such a way that the
loop (4) lies concentric to the hole in the floor plate.
Use the gravel bed below the product to drain away
the condensate.
0020257297_07 Installation and maintenance instructions
Condition: Version with drain pipework
Install the supplied condensate discharge tundish (3)
and adapter (2).
Connect the drain pipework to the adapter and to a
downpipe. In doing so, ensure that there is a sufficient
downward gradient.
Slide the heating wire (1) from inside through the con-
densate discharge tundish and the adapter and into
the drain pipework.
Adjust the internal heating wire in such a way that the
loop (4) lies concentric to the hole in the floor plate.
If the region is one with ground frost, install electrical
trace heating for the drain pipework.
Validity: Flat roof installation
Condition: Version without drain pipework
Install the supplied condensate discharge tundish (3).
Slide the heating wire (1) from inside through the con-
densate discharge tundish and to the outside.
Adjust the internal heating wire in such a way that the
loop (4) lies concentric to the hole in the floor plate.
Use the flat roof to drain away the condensate.
Condition: Version with drain pipework
Install the supplied condensate discharge tundish (3)
and adapter (2).
Connect the drain pipework to the adapter and to a
downpipe over a short distance. In doing so, ensure
that there is a sufficient downward gradient.
Slide the heating wire (1) from inside through the con-
densate discharge tundish and the adapter and into
the drain pipework.
Adjust the internal heating wire in such a way that the
loop (4) lies concentric to the hole in the floor plate.
If the region is one with ground frost, install electrical
trace heating for the drain pipework.
4.12

Setting up a protective wall

Validity: Floor installation OR Flat roof installation
If the installation site is not protected against the wind,
set up a protective wall against the wall.
Comply with the minimum clearances.
4.13

Removing/installing the casing sections

The following work must only be carried out when required or
during maintenance work or repair work.
59

Advertisement

Table of Contents
loading

This manual is also suitable for:

Arotherm vwl 55/5 as 230v s2Arotherm vwl 75/5 as 230v s2Arotherm vwl 105/5 as 230v s2Arotherm vwl 105/5 as s2Arotherm vwl 125/5 as 230v s2Arotherm vwl 125/5 as s2

Table of Contents