6.3
Installing components for the energy supply
company lockout function
With the energy supply company lockout function, the heat
generation from the heat pump can be switched off tempor-
arily by the energy supply company. The unit can be shut
down in two ways:
1.
The signal for the shutdown is fed to connection S21
for the indoor unit.
2.
The signal for the shutdown is fed to a partition that is
installed on-site in the meter/fuse box.
If the energy supply company lockout function is
provided, install and wire additional components in the
building's meter/fuse box.
To do this, follow the wiring diagram in the appendix of
the installation instructions for the indoor unit.
6.4
Removing the cover for the electrical
connections
B
Remove the cover, as shown in the figure.
6.5

Stripping the electrical wire

1.
If required, shorten the electrical wire.
30 mm
L
N
PE
40 mm
+
-
30 mm
2.
Strip the outer sheathing from the electrical wire. In
doing so, ensure that the insulation on the individual
conductors is not damaged.
3.
To avoid short circuits resulting from loose individual
wires, fit conductor end sleeves on the stripped ends of
the conductors.
66
6.6
6.6.1
1.
A
2.
3.
4.
5.
6.
6.6.2
1.
2.
3.
4.
5.

Establishing the power supply, 1~/230V

Determine the type of connection:
Case
Energy supply company lockout not
provided
Energy supply company lockout
provided, shutdown via connection
S21
Energy supply company lockout
provided, shutdown via partition
1~/230V, single power supply
If it is stipulated for the installation site, install one re-
sidual-current circuit breaker for the product.
5
4
N
X200
L3
3
L2
2
L1
1
2
L
X210
N
1
L
4
N
3
X211
2
1
Install a disconnector for the product in the building.
Use one 3-pole power supply cable.
Route the power supply cable from the building and
through the wall duct to the product.
Connect the power supply cable to connection X200.
Use the strain relief clamp to secure the power supply
cable in place.
1~/230V, dual power supply
If it is stipulated for the installation site, install two re-
sidual-current circuit breakers for the product.
5
4
N
X200
L3
3
L2
2
L1
1
2
L
X210
N
1
L
4
N
3
X211
2
1
Install two disconnectors for the product in the building.
Use two 3-pole power supply cables.
Route the power supply cables from the building and
through the wall duct to the product.
Connect the power supply cable (from the heat pump
electricity meter) to connection X200. This power sup-
ply may be temporarily switched off by the energy sup-
ply company.
Installation and maintenance instructions 0020257297_07
Connection type
Single power supply
Dual power supply
N
L
N
L
L
N

Advertisement

Table of Contents
loading

This manual is also suitable for:

Arotherm vwl 55/5 as 230v s2Arotherm vwl 75/5 as 230v s2Arotherm vwl 105/5 as 230v s2Arotherm vwl 105/5 as s2Arotherm vwl 125/5 as 230v s2Arotherm vwl 125/5 as s2

Table of Contents