Installation; Unpacking; Location Requirements; Locate And Install The Ram - Graco Therm-O-Flow 20 EasyKey NXT 2200 Instructions-Parts List Manual

Hot melt pail unloaders
Table of Contents

Advertisement

Installation

The installation procedure includes:
unpacking the ram
locating and installing the ram
mechanical setup
electrically connecting hoses to the electrical control
panel
grounding the system
connecting the electrical control panel to a power
source
connecting to an air source
setting controls on the electrical control panel

Unpacking

1. Inspect the shipping box carefully for damage. Con-
tact the carrier promptly if there is damage.
2. Open the box and inspect the contents carefully.
There should not be any loose or damaged parts in
the box.
3. Compare the packing slip against all items in the
box. Report any shortages or other inspection prob-
lems immediately.

Location Requirements

Refer to the Dimensions drawing on page 76 for ram
mounting and clearance dimensions.
1. Make sure there is sufficient overhead clearance for
the pump and ram when the ram is in the fully raised
position (approximately 82 in. [209 cm]).
2. If you are installing a vent hood, make sure there is
sufficient horizontal clearance for it. Locate the ram
near a connection to the factory ventilation system.
3. Make sure the air regulators for the pump and ram
are fully accessible, with room to stand directly in
front of the pneumatic control panel and the electri-
cal control panel.
4. Make sure there is easy access to an appropriate
electrical power source. The National Electrical
Code requires 3 ft (0.9 m) of open space in front of
the electrical panel.
311976A

Locate and Install the Ram

1. Apply 50 psi download pressure to ram.
CAUTION
Always lift system at proper lift locations (see F
Do not lift in any other way.
2. Attach a lifting sling at the proper lift spots (see F
3). Lift off the pallet using a crane or a forklift.
To mount the ram directly to the floor, remove the
four wheels.
3. Position the ram in the desired location.
4. Lock the wheels, or bolt the ram to the floor. To bolt
the ram to the floor, level the base using metal
shims. Bolt the ram to the floor, using anchors that
are long enough to prevent the unit from tipping.
Lift Locations (if air is supplied to the
system and ram lever is set to down)
F
. 3: Lift Locations
IG
Installation
. 3).
IG
.
IG
TI10078A
11