Installation Of The Outdoor Unit - Gree SUPER+ MULTI ULTRA Series Service Manual

Table of Contents

Advertisement

Super Free Match
Service Manual

3.9 Installation of the Outdoor Unit

1)
Check the installation location and ensure it is strength and level, so that the unit will not cause any
operating vibration or noise after installation.
2)
In accordance with the foundation drawing in the following figure, please drill 4 holes in the installation
location.
3)
Fix the unit securely with the foundation bolts. You can get the M10 or M8 foundation bolts, nuts and
washers from the market.
4)
Rubber or spring shock absorbers should be used during the installation of the outdoor unit to meet the
noise and vibration requirements.
5)
Screw the foundation bolts into the ground and it is better that their length is less than 20mm from the
foundation face.
INSTALLATION
62
A: The outlet side
B: Bottom view (mm)
C: Drain hole