Section D - Installing the current transformers
Consumption CT installation
in grid-tied systems (load only configuration)
Consumption CTs are installed on the home loads panel when a site
needs to only monitor the consumption by the home loads.
Make sure that the main load center wires are de-energized until you
have secured the CT wires in the terminal blocks .
Clamp the red and black C1 CT on the load center feed wire Line 1
(matching the IQ Gateway's "L1" voltage terminal) with the CT arrow
pointing toward the load (away from the grid).
Wh
Grid
Utility meter
Risk of electrocution and equipment damage! Do not install CTs when
current is flowing in the sensed circuit. Always install CT wires in the
terminal blocks before energizing the sensed circuit.
IQ Combiner 5/5C Quick Install Guide
Main load
center
Home loads
Clamp the purple and brown C2 CT on the load center feed wire
Line 2 (matching the IQ Gateway's "L2" voltage terminal) with the
CT arrow pointing toward the load (away from the grid).
Tighten all connections using a 5 in-lbs torque.
IQ Gateway Terminal Block
CU,
C,
AWG MIN
MEAS CAT III
OVC III
PD, B
OVC II
Brown
Purple
Red
Black