Section D - Installing the current transformers

Consumption CT installation in

grid-tied systems (load with solar configuration)

Consumption CTs are installed on the service entrance when a site
requires to monitor the net import/export to the grid.
This is mandatory on sites where power export limiting (PEL)
restrictions must be met.
Make sure that the main load center wires are de-energized until you
have secured the CT wires in the terminal blocks.
Grid
Risk of electrocution and equipment damage! Do not install CTs when
current is flowing in the sensed circuit. Always install CT wires in the
terminal blocks before energizing the sensed circuit.
33
Main load
center
Wh
Utility Meter
Clamp the red and black C1 CT on the load center feed wire Line 1
(matching the IQ Gateway's "L1" voltage terminal) with the CT arrow
pointing toward the load (away from the grid).
Clamp the purple and brown C2 CT on the load center feed wire
Line 2 (matching the IQ Gateway's "L2" voltage terminal) with the
CT arrow pointing toward the load (away from the grid).
Tighten all connections using a 5 in-lbs torque.
IQ Gateway Terminal Block
CU,
C,
AWG MIN
MEAS CAT III
OVC III
PD, B
OVC II
Brown