7 BEFORE INSTALLATION

7.1 TRANSPORTATION AND HANDLING

C A U T I O N
7.1.1 Transportation of indoor unit
Transport the product as close to the installation location as
possible before unpacking.
Do not put any material on the indoor unit.
The indoor unit is packed upside down and therefore the
foamed polyethylene drain pan is exposed at the upper side.
Do NOT put the indoor unit with the drain pan side down
during the process from unpacking the indoor unit to hanging
up the unit to a ceiling. In addition, do NOT handle the indoor
unit by the drain pan portion or the air outlet portions.
As foamed polyethylene is used for the indoor unit, take care
when handling the indoor unit. Applying an excessive force
to the unit may cause a breakage.

8 INDOOR UNIT INSTALLATION

D A N G E R
9
PMML0515 rev.0 - 03/2019
7.1.2 Handling of indoor unit
D A N G E R
C A U T I O N
N O T E
For concrete slab
I-Beam
Steel
Suspension bolts
Anchor bolt
(W3/8 or M10)
C A U T I O N
Wooden bar
(60mm to 90mm square)
Concrete
Nuts
washers
Wooden beam
Sling bolt
(W3/8 or M10)