Sidewall Termination Installation - State Water Heaters 301 Series Instruction Manual

Hide thumbs Also See for 301 Series:
Table of Contents

Advertisement

24 INCHES (61 cm) MINIMUM
48 INCHES (122 cm) IN COLDER CLIMATES
FIELD
SUPPLIED
90° ELBOW
VENT (EXHAUST)
TERMINATION
FACTORY SUPPLIED
STANDARD TERMINATIONS
POINTED DOWNWARD
FIELD SUPPLIED
PLUMBING
ROOF BOOTS
OR FLASHINGS
Figure 24. Vertical Termination - Direct Vent

SIDEWALL TERMINATION INSTALLATION

1. Determine the location for the termination(s).
INTAKE AIR
2. If installing only vent (exhaust) piping in a Power Vent
TERMINATION
configuration through a sidewall; ensure that all exterior sidewall
clearance requirements for the termination, shown in
(page 37), are being maintained. These clearances and those
cited by local and national codes must be maintained.
MAINTAIN 12" (30 cm)
3. If installing both the intake air and the vent piping in a Direct
18" (45 cm) FOR CANADA
Vent configuration through a sidewall; ensure that all exterior
MINIMUM CLEARANCE
sidewall clearance requirements for the terminations, shown in
ABOVE HIGHEST
ANTICIPATED SNOW LEVEL.
Figure 52
are being maintained. These clearances and those cited by local
and national codes must be maintained.
4. If installing both an intake air and vent termination in a Direct
Vent configuration through a sidewall there must be a minimum
of 24 inches (61 cm) separation, measured on vertical center
line, between the intake air and vent terminations, see
Note: In colder climates this separation should be
5. If installing both intake air and vent terminations in a Direct
Vent configuration through a sidewall the intake air and vent
terminations must be installed at the same elevation measured
on horizontal center line - see
6. When the intake air and/or vent piping from multiple water
heaters will terminate at the same location through a sidewall,
the vent terminations can be grouped together in close proximity
- 0 inches/touching. The intake air terminations can also be
grouped together in close proximity - 0 inches/touching.
• However, the distance between the closest vent and
7. Cut a hole in the wall through which the pipes will pass as
follows:
Note: Beware of concealed wiring and piping when
8. Cut a length(s) of pipe being installed 3.5 inches (8.9 cm) to 9.5
inches (24.1 cm) longer than the wall thickness at the opening.
27
(page 38), for the vent and the intake air termination
increased to at least 48 inches (122 cm) between
the intake air and vent termination or any other
appliance vent that discharges moisture-laden
air such as clothes dryers. This will reduce
possibility of frost over from side winds blowing
exhaust vapors to the intake air termination and is
recommended for Canadian installations.
Figure 25
VENT (EXHAUST)
TERMINATION
ELEVATION
INSTALL ON
CENTERLINE
KEEP INTAKE AND VENT
TERMINATION SCREENS
CLEAR OF DEBRIS
24 INCHES (61 cm) MINIMUM
48 INCHES (122 cm) IN COLDER CLIMATES
Figure 25. Side-Wall Termination - Direct Vent
intake air terminations must be a minimum of 24 inches
(61 cm). In colder climates this separation should be
increased to at least 48 inches (122 cm). See
(page 27).
Pipe Size
2"
3"
4"
cutting through the wall.
Figure 51
Figure 25
.
INTAKE AIR
TERMINATION
Figure 25
Hole Size
3" (7.6 cm)
4" (10 cm)
5" (13 cm)
.