10
Maintenance
WARNING!
Burns hazard. The valves and piping may be very hot. Wear protective
gloves
2. CLEANING AWAY DEPOSITS:
- Thoroughly wash and clean all the valve parts before disassembly;
- Pay attention to any possible detergent or other aggressive 昀氀uid
deposits (see "Cleaning");
- Always use protective safety glasses and gloves when required.
3. REPLACEMENT OF WORN VALVE PARTS:
Always use original spare parts

10.2 Scheduled maintenance

SCHEDULED MAINTENANCE
VALVE GASKETS
Preventive
Replace after 12 months
In the event of leaks
Replace at the end of the day
Check correct operation and that there are no leaks
Periodical
Record the actions carried out
EN-IST-BBZM-0123
19