5. Complete the reinstallation of the controller module:
a. With the cam handle in the open position, firmly push the controller module in until it meets
the midplane and is fully seated, and then close the cam handle to the locked position.
Do not use excessive force when sliding the controller module into the
chassis to avoid damaging the connectors.
The controller begins to boot as soon as it is seated in the chassis.
b. If you have not already done so, reinstall the cable management device.
c. Bind the cables to the cable management device with the hook and loop strap.
You must look for an Automatic firmware update console message. If the
update message appears, do not press
process until after you see a message confirming that the update is
complete. If the firmware update is aborted, the boot process exits to the
LOADER prompt. You must run the
enter
Important: During the boot process, you might see the following prompts:
• A prompt warning of a system ID mismatch and asking to override the system ID. Respond
this prompt.
• A prompt warning that when entering Maintenance mode in an HA configuration you must
ensure that the healthy controller remains down. Respond

5.3.4. Restore and verify the system configuration - DM3010H

After completing the hardware replacement and booting the replacement
controller, verify the low-level system configuration of the replacement controller
and reconfigure system settings as necessary.

Step 1: Set and verify system time after replacing the controller

You should check the time and date on the replacement controller module against the healthy
controller module in an HA pair, or against a reliable time server in a stand-alone configuration. If
the time and date do not match, you must reset them on the replacement controller module to
prevent possible outages on clients due to time differences.
About this task
It is important that you apply the commands in the steps on the correct systems:
• The replacement node is the new node that replaced the impaired node as part of this
procedure.
58
to reboot the system.
bye -g
to interrupt the boot
Ctrl-C
command, and then
update_flash
to this prompt.
y
to
y