Download Print this page

ABSCO SHEDS GCPSN2 Manual page 11

Gable carport

Advertisement

NOTE: Throughout frame construction the structure will be unstable until construction is fully
completed. Make sure during construction framework is braced using rope or timber props to
stabilise and prevent twisting or collapse. Assemblies are too heavy for 1 person to lift unaided.
POSTS
Please
refer
engineering
drawings
that specify concrete
footings / slab and post
distances.
FITTING END TRUSS TO POSTS
Post
FITTING EDGE BEAM
1
80
40
80
3
Absco Industries
Assembly Instruction Manual
ABSCO GABLE CARPORT
MODEL: GCPSN2
3.0mW x 6.0mD x 2.66mH
to
3
1. Place the posts on the
2900
2750
foundation, use the dimensions
shown to confirm correct
placement.
Position each column with the
6400
top bracket to the centre.
Mark out the base bracket hole
positions on the concrete.
Using a 12mm masonry drill bit,
drill the anchor holes and secure.
Safely lift a truss and place on
top of a pair of posts.
Make sure the outside of post
and end of truss are flush.
Fasten with 6 hex head tek
screws in the MPB and into the
truss.
Do this for both end trusses.
1. Safely lift and align the edge
beam as shown. It has to sit 80
2
mm below the post as shown.
Fasten to the column with 10 hex
head tek screws.
2. After both ends of the beam
are secured, refit the outer
pieces of edge beam ZACO117.
Remember wafer head teks for
the top side.
3. Close both ends of the edge
beam with an end cap ZACO155
and two tek screws.
Model: GCPSN2
8/6/23
11

Advertisement

loading