5
Installing a Device
5.3 Installing a Device in an ETSI 21-Inch Cabinet
with Middle Columns
Install floating nuts onto the cabinet.
1
2
Install the cable management frame
and power cable tray onto the device.
Remove the mounting ear on
3
the left side of the chassis,
move it to the middle of the
panel, and install an ETSI
conversion mounting ear.
Then, take out a 19-inch
mounting ear and an ETSI
conversion mounting ear
from the auxiliary material
package and install them on
the right side of the chassis
(that is, the side with a cable
management frame).
Floating nut
Installation hole
M3
2
M6
1