Prerequisites
● Wear personal protective equipment and use dedicated insulated tools to avoid
6.1 Check Before Power-on
No.
1
2
3
4
5
6
7
Issue 07 (2023-04-30)
D ANGER
electric shocks or short circuits.
Acceptance Criteria
The solar inverter is installed correctly and securely.
The DC switches and the downstream AC switch are OFF.
All cables are connected correctly and securely.
The installation space is proper, and the installation environment
is clean and tidy.
The maintenance compartment door is closed and the screws are
secured.
Unused DC input terminals are sealed.
Unused USB and RESET ports are plugged with watertight caps.
Copyright © Huawei Technologies Co., Ltd.
6
Commissioning
6 Commissioning
75