Step 6 Use an insulation resistance tester to test the insulation resistance between the
PV– cables and the ground: Add 1500 V DC voltage between the PV– cables and
the ground and check the insulation resistance.
Step 7 Insert the positive and negative connectors into the corresponding DC positive and
negative input terminals of the solar inverter.
Issue 07 (2023-04-30)
If the insulation resistance is greater than or equal to 1 MΩ, it is normal.
If the insulation resistance is less than 1 MΩ, troubleshoot the cable
insulation.
Figure 5-21 Testing the insulation resistance
NO TE
You can use a self-made tool to connect all PV– cables together through an adapter to
test the insulation resistance between all PV– cables of a device and the ground at a
time.
Figure 5-22 Testing the insulation resistance between all PV– cables and the
ground
Copyright © Huawei Technologies Co., Ltd.
5 Electrical Connections
63

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sun2000-110ktl-m2Sun2000-115ktl-m2

Table of Contents