SECTION 2 – INSTALLATION
2.5.2 BMK 1500 – 3000 Lifting Provisions
Three lifting lugs are provided at the top of the primary heat exchanger as shown in Figure 2-3b.
Remove the front top panel from the unit to provide access to the lifting lugs. Remove the four
(4) lag screws securing the unit to the shipping skid. Lift the unit off the shipping skid and
position it on the 4 inch to 8 inch (10.2 cm to 20.3 cm) housekeeping concrete pad (required)
in the desired location.
Figure 2-3b: Boiler Lifting Provisions – BMK 1500/2000 Shown
OMM-0121_D • GF-205 • 5/9/2019
LIFTING LUGS (3 POSITIONS)
Technical Support • (800) 526-0288 • Mon-Fri, 8 am - 5 pm EST
YELLOW ARROWS
2" NATURAL
GAS OR 1"
PROPANE GAS
INLET