BEFORE YOU START PLEASE READ INSTRUCTIONS CAREFULLY
- Check the pack and make sure you have all the parts listed.
- When you are ready to start, make sure you have the right tools at hand (not supplied)
including a Phillips screwdriver, Stanley knife, wood saw, step ladder and drill with 2mm
bit.
- Ensure there is plenty of space and a clean dry area for assembly.

TIMBER

As with all natural materials, timber can be a ected during various weather conditions.
For the duration of heavy or extended periods of rain, swelling of the wood panels may
occur. Warping of the wood may also occur during excessive dry spells due to an interior
moisture loss. Unfortunately, these processes cannot be avoided but can be helped. It is
suggested that the outdoor building is sprayed with water during extended periods of
warm sunshine and sheltered as much as possible during rain or snow.
Our buildings are pre treated with a water based treatment**; this only helps to protect
the product during transit and for upto 3 months against mould. To validate your
guarantee and ensure longevity of the product, it is ESSENTIAL the building is treated
with a wood preserver within the rst three months of assembly and thereafter in
accordance with the manufactures recommendations. Care must be taken to ensure
the product is placed on a suitable base.

BUILDING A BASE

When thinking about where the building and base is going to be constructed:
Ensure that there will be access to all sides for maintenance work and annual
treatment.
Ensure the base is level and is built on rm ground, to prevent distortion. Refer to
diagrams for the base dimensions, The base should be slightly smaller than the external
measurement of the building, i.e. The cladding should overlap the base, creating a run
o for water. It is also recommended that the oor be at least 25mm above the
surrounding ground level to avoid ooding.

TYPES OF BASE

- Concrete 75mm laid on top of 75mm hard-core.
- Slabs laid on 50mm of sharp sand.
Whilst all products manufactured are made to the highest standards of Safety and in
the case of childrens products independently tested to EN71 level, we cannot accept
responsibility for your safety whilst erecting or using this product.
Refer to the instructions pages for you speci c product code
Please retain product label and instructions for future reference
x2
All building's should be
erected by two adults
For ease of assembly, you
MUST pilot drill all screw
holes and ensure all screw
heads are countersunk.
2mm Drill bit
Pressure Treated Timber
Pressure treating is a chemical process which helps to protect wood against adverse weather which could
lead to rot or insect damage.
The most common chemicals used to pressure treat wood are Alkaline Copper Quaternary (ACQ),
Copper Azole (CA), and Micronized Copper Quaternary (MCQ).
Safety: Always wear gloves, eye protection and a dust mask when handling wood. Due to chemicals in
pressure treated wood, never burn its sawdust or scraps; instead dispose in a land ll.
For assistance please contact customer care on: 01636 880514
Mercia Garden Products Limited,
Sutton On Trent,
Newark,
Nottinghamshire,
NG23 6QN
www.merciagardenproducts.co.uk
Winter = High Moisture = Expansion
Summer = Low Moisture = Contraction
CAUTION
Every e ort has been made during the
manufacturing process to eliminate the
prospect of splinters on rough surfaces of the
timber. You are strongly advised to wear gloves
when working with or handling rough sawn
timber.

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the 01PTOSBRA1008SDFW-V1 and is the answer not in the manual?

Questions and answers

Summary of Contents for Mercia Garden Products 01PTOSBRA1008SDFW-V1

  • Page 1 For assistance please contact customer care on: 01636 880514 - Concrete 75mm laid on top of 75mm hard-core. - Slabs laid on 50mm of sharp sand. Mercia Garden Products Limited, Sutton On Trent, Whilst all products manufactured are made to the highest standards of Safety and in...
  • Page 2 01PTOSBRA1008SDFW-V1 Please retain product label and instructions for future reference Overall Dimensions: Nail Bag Felt Tacks x 120 Length = 2482mm 20mm Screw x 12 Width = 3027mm Height = 2339mm 30mm Black Screw x 2 Base Dimensions: 30mm Screw x 162...
  • Page 3 Please retain product label and instructions for future reference Step 1 Step 3 Place the oor on a rm and level base, Place the remaining back panel ensure the base has suitable drainage free and remaining plain gable on from areas where standing water can collect. the oor and x the corners See the front page for base requirments.
  • Page 4 Please retain product label and instructions for future reference Step 5 Step 7 Position the two parts of the ridge bar Fix the support block to the side panel within the U channel and secure from framing with 2 x 50mm screws. Position either side with 3 x 30mm screws and 4 x the block at the top of the framing with 30mm screws from underneath.
  • Page 5 Please retain product label and instructions for future reference Step 9 Step 11 Repeat step 10 for the four remaining roof panels. Ensure they Repeat steps 5,6 and 7 for the two sit ush to the centre truss and plain remaining truss, supports and gables.
  • Page 6 Please retain product label and instructions for future reference Step 13 nce the roof os attached the panels can be xed to the oor panel using 4x50mm screws per panel. 24x50mm Screws 50mm Pre drill screw hole Step 14 Cut out three strips of 3128mm felt an place onto the roof.
  • Page 7 Please retain product label and instructions for future reference Step 15 Step 17 e cover trims to the front back se 4x30mm screws to x each Fit th and sides of the building using beading strip onto the door panel. 3x30mm screws per cover trim.
  • Page 8 Please retain product label and instructions for future reference It is ESSENTIAL that you apply wood treatment immediately after the building has been assembled. AFTER TREATMENT: score around protective cover on glazing and carefuly peel covering back...

Table of Contents