3. FINAL CHECK
This chapter describes the instructions to check that all the connections and settings have been
successfully done.
1) Verify that the CAN communication cable from the battery to the inverter is connected.
2) Verify that the inverter is ON.
3) Access to the inverter and verify that there is no "Communication Error with BMS" alarm
3.1 Configuration of the battery settings
After the commissioning of the final check, it is necessary to configure the SOC levels in the
inverter.
CONFIGURATION > 01 BATTERY
Setting
Maximum SOC
Minimum SOC
ABS2015IMC04_.docx
Description
Maximum state of charge for charging the batteries from the photovoltaic
energy (%).
Charge status under which battery discharge is not allowed when the grid
is available.