Load Management
Dual Floor Pro Earth
Dynamic Load Management
For dynamic load management to work the Modbus Meter must be installed correctly and
the following setting must be set:
- Enable Power Allocation - Enabled
- External current sampling method - Meter
- External monitored max input power (kw) - main fuse size
- Meter Address - Side Of Meter
External monitored max input power is measured in kw and must be set to the main fuse
size so that if the load on the property was to reach the limit set the charger would reduce
it's output accordingly to not exceed the property main fuse.
60A = 13kw
80A = 18kw
100A = 23kw
Static Load Management
For installations where dynamic load management is not possible you can hard limit the
charger using setting 'charger maximum output current (A)' - As default this will be 32A,
however can be downrated to as low as 6A (1.76kw) if required and anything inbetween.
11