Equipment Installation

Install the management server in the cabinet

Verifying the mounting kit parts

VxRack Node Hardware Installation Guide
32
Figure 9 Inner rail over the first part of ball bearing retainer assembly
9. Once the inner rails are properly engaged with the ball bearing retainer
assemblies, push the server into the cabinet until the slide rails are engaged and
locked.
An audible click indicates that the slide rails are engaged and locked.
10. On the outside of each rail assembly, slide the white disconnect tab forward to
unlock the server, and push the server completely into the cabinet so that front
on server is flush with cabinet.
11. Secure the server to the front of the cabinet with the two screws (one on each
side).
12. Repeat this procedure to install remaining D51B-1U servers.
13. If you are installing an AMS supported version (1.33.X), refer to the latest
VxRack Node Deployment Guide .
14. If you are installing an SW only version (1.32.X), refer to the latest Quick Start
Guide:
VxRack Node Quick Start Guide for 2-Layer (VxRack Nodes with SLES12 and
l
Storage Clients on ESX).
VxRack Node Quick Start Guide for VMware (VxRack Nodes with ESX and are
l
also Storage Clients).
Verify that the server mounting kit includes the parts listed in table that follows.
Table 9 Mounting kit parts
Component
2 universal rail assemblies
(consists of slide rails for connection to the
cabinet and inner rails for connection to
server)
Use
Attach back to front on either side between
cabinet channels