of diagram IN-H66-039-13. (Note that you have to trim the decorative molding)
Install the tunnel using the bolts and nuts as show in the diagram IN-H66-039-13.
Step 12
Approach Side Panel Installation
Refer Drawing IN-H66-039-012 page A-167.
Start with the side from the foul line, with item #4, the plastic molding must be flush with the top of the
approach, so be sure to adjust the high of the panel before you fixing it in place.
Counter sink 6 holes per side panel refer to detail B of drawing IN-H66-039-006A page A-159 use drywall
screw #6 x 1 5/8".
Item #5 in front of the approach must be cut to fit each side of the Ball return Hood.
Install the finishing molding of the 2 3/4" capping (Item #11) and the one of the ball track (Item #12 and 13)
Step 13
Lateral Safety Guard Installation (Optional)
The kit includes 6 sections, start by assembling 3 sections with their legs, use the approach leg for the first section.
Refer to diagram IN-Q200-1010-40 page A-173 for details.
Fix the first 3 sections on the side of the lane as show in diagram IN-H66-039-014 page A-169, then fix the last 3
sections, install the decals as show in the same diagram.
Step 14
Scoring Connections
Refer to drawing IN-ME-B03-003 and IN-ME-B03-004 page A-179 and A-180 to make all connections.
Step 15
Union Kit Installation
Drawing IN-H66-039-025 page A-170 and IN-H66-039-026 page A-171
When you multiple unit to install you must use the union kit, to make the joint between two units.
Install the monitors post as show in detail C of the diagram IN-H66-039-025 page A-170, note that you have to
install only one post between two units.
Cut the lane side panel in two long parts; screw those parts on the side of the lane at 1 1/8" from top of the lane. Once
you have those parts screw in place screw the union finishing panel on top of those parts.
diagram IN-H66-039-025 page A-170)
On the approach frame you have to move the sleeper on each frame that make the union, (See Detail A of the
diagram IN-H66-039-025 page A-170).
Install the approach union panel support item #2 as show in detail B of drawing IN-H66-039-026 page A-171.
Install the pit frame union plank item #6 as show in detail A of drawing IN-H66-039-026 page A-171.
Once the kickback are all installed, screw in place the front kickback union panel item #7.