5. INSTALLATION OF THE MACHINE

5.1 Preparation

5.1.1 The machine size and weight measurements, given the technical specification sheet.The ground, where the
machine will be placed, should be even, solid enough to bear the weight of the machine.
5.1.2 The machine should be located approx. 50 cm away from the rear wall.
5.1.3 You can provide the balance of the machine with adjustable counterforts (PICTURE 2 NO 64) in the bottom
part.

5.2 Connecting to Power Source

5.2.1 The Electrical connection must be made by a licensed electrician
5.2.2
The power outlet socket on the machine should be available.
5.2.3 Plug the machine to a grounded socket.
5.2.4 Main voltage of the machine is optional as 400 V 50 Hz.
5.2.5 Check the power source voltage. It has to be in accordance with the values stipulated on the machine's
type label
5.2.6 After electrical connection is made, machine must be operated in idle running and it must be controlled whether
rotation directions of cutting tools are correct or not and if the rotation direction is wrong, appropriate connection
must be made.