DISCLAIMER EG4 reserves the right to make changes to the material herein at any time without notice. You may refer to the EG4 website at www.eg4electronics.com for the most updated version of our manual.
SPECIFICATIONS MODEL RATED OUPUT POWER 6000W PV INPUT (DC) Max. PV Power 7500W Max. Input voltage 500 VDC (Maximum PV open voltage) DC Power MPPT range VDC~480 VDC Working MPP range 120 VDC~480 VDC Max. DC Input current / Number of MPP Tracker GRID-TIE OPERATION GRID OUTPUT (AC) Nominal Output Voltage...
INTRODUCTION This is a residential self-consumption multi-function inverter, combining the functions of an inverter, solar charge controller, and battery charger to offer uninterrupted power system in a single package. The comprehensive LCD display offers user-configurable and easily-accessible button operations such as battery charging current, AC or solar charging priority, and acceptable input voltage based on different applications.
Product Overview NOTE: For parallel installation and operation, refer to the commissioning guide and connection diagrams. LCD display Status indicator Charging indicator Fault indicator Function buttons Power on/off switch AC input connectors AC output connectors (Load connection) PV connections 10. Battery connections 11.
INSTALLATION Unpacking and Inspection Before installation, please inspect the unit. Be sure nothing inside the package is damaged. Check to ensure the following items are included with each inverter: Inverter unit Software CD Manual RS-232 Cable Battery Comms Cable Parallel Cables Preparation To prepare for the wiring step of installation, remove the bottom cover as shown below.
Mounting the Inverter Install the unit using all three screw holes. Use #8 (M4) or #10 (M5) screws. Battery Connection CAUTION: For safe operation and regulation compliance, it is required to install a separate DC over-current protector or disconnect device between battery and inverter. It may not be required to have a disconnect device in some applications, however, you are required to have over-current protection installed.
WARNING: Shock Hazard Installation must be performed carefully; arc and shock hazards are present. CAUTION! Do not place anything between the flat part of the inverter terminal and the ring terminal. Mixed materials, gaps, and loose connections can all lead to overheating. CAUTION! Do not apply anti-oxidant substance on the terminals before terminals are connected.
WARNING: Ensure all AC power sources and loads are disconnected before wiring the unit. 4. Insert the AC output wires according to labeling on the terminal block and tighten terminal screws. Be sure ) first. to connect the grounding conductor ( →...
CAUTION: It is required to use a PV surge protection device. Damage to the inverter can occur from surges such as lighting or short circuits. Model Typical Amperage Cable Size Torque 10AWG ~17-21 in-lbs (-2.0-2.4Nm) PV Module Selection: 1. Open Circuit Voltage (Voc) of the PV modules/strings must not exceed the unit's maximum rating. Voc must be calculated including the environmental impacts, such as temperature in accordance to the module manufacturer's data sheet and reliable weather data for the installation location.
Communication Connection Serial Connection Please use the supplied communication cable to connect to inverter and PC. Insert the bundled CD into a computer and follow the on-screen instructions to install the monitoring software. For the detailed software operation instructions, please check the user manual of the software stored on the CD. Wi-Fi Connection Wi-Fi module can enable wireless communication between off-grid inverters and the cloud monitoring platform.
OPERATION Power ON/OFF After completing installation of the unit, the next step is powering on for setup. Start by pressing the On/Off switch (located on display unit) to power on the system. Operation and Display Panel Refer to the diagram and table below for details on the operation and display panel. There are three indicators, four function keys, and an LCD display.
Function Keys Function Key Description Exit the setting/go back Reserved Reserved Reserved Reserved Scroll to previous selection Down Scroll to next selection Enter To confirm/enter the selection in setting mode LCD Display Icons Icon Function Input source information Indicates AC input information is being displayed Indicates PV1 input information is being displayed (PV2 not used) Left digital display information Indicates input voltage, input frequency, battery voltage, PV...
Load information Indicates output overload. Indicates the load level by 0-24%, 25-49%, 50-74%, and 75-100%. 0%~24% 25%~49% 50%~74% 75%~100% Mode operation information Indicates connection to an AC input source. Indicates connection of the PV array. Indicates solar is being used to charge the battery bank. Indicates the DC/AC inversion is working.
Page 16
Appliances If selected, acceptable AC input (Default setting) voltage range will be set to 65-140VAC. AC input voltage range If selected, acceptable AC input voltage range will be set to 95-140VAC. 110Vac 120V (Default setting) Output voltage 50Hz 60Hz (Default setting) Output frequency Available power will Solar energy provides power to...
Page 17
If this inverter/charger is working in Line, Standby or Fault mode, charger source can be programmed as below: Solar first Solar energy will charge battery as first priority. Utility/AC input will charge battery only when solar energy is not available. Solar and Utility Solar energy and utility/AC input will Charger source priority:...
Page 18
Setting range is from 44V to 51V connected. and each click is an increment of default setting: 46V In EG4 Mode you will see a Bypass loads to grid when percentage instead grid is present. Battery fully charged...
Page 19
Return to default If selected, no matter how users display screen (default) switch display screen, it will automatically return to default display screen (Input voltage /output voltage) after no button is Auto return to default display screen pressed for 1 minute. Stay at latest screen If selected, the display screen will stay at latest screen user selects...
Page 20
00:00 (default setting) Scheduled Start charging time for AC charger The setting range of starting time for the AC charger is from 00:00 to 23:00, each click is 1 hour. 00:00 (default setting) Scheduled Stop charging time for AC charger The setting range of stop charging time for AC charger is from 00:00 to 23:00, each click is 1 hour.
Display Setting The LCD display information is cycled through by pressing “UP” or “DOWN” keys. The selectable information is switched as below order: input voltage, input frequency, PV voltage, charging current, battery voltage, output voltage, output frequency, load percentage, load in watts, load in VA, load in watts, DC discharging current, main board firmware version and SCC firmware version.
Page 22
Input 2 frequency=60.0Hz, output 2 frequency=60.0Hz Input 2 frequency and output 2 frequency Battery Voltage=48.0V, output 1 voltage=120V Battery voltage and output 1 voltage Battery Voltage=48.0V, output 2 voltage=120V Battery voltage and output 2 voltage Battery Voltage=48.0V, load 1 percentage = 68% Battery voltage and load 1 percentage...
Page 23
Battery Voltage=48.0V, load 2 percentage = 68% Battery voltage and load 2 percentage Battery Voltage=48.0V, load 1 in VA=1.08kVA Battery voltage and load 1 in VA Battery Voltage=48.0V, load 2 in VA=1.08kVA Battery voltage and load 2 in VA Battery Voltage=48.0V, load 1 in Watt=1.88kW Battery voltage and load 1 in watts...
Page 24
Battery Voltage=48.0V, load 2 in Watt=1.88kW Battery voltage and load 2 in watts PV1 Voltage=360V, PV power=1.58kW PV1 voltage and PV power Charging current=30A, discharging current=0A Charger current and DC discharging current Daily production example = 6.3kWh PV energy generated today...
Page 25
Monthly energy example = 358kWh PV energy generated this month Yearly energy example = 8.32MWh PV energy generated this year Total energy example = 13.9MWh Lifetime PV energy generated Date example Nov 28, 2016. Date...
Time example 13:20. Time (24HR format) Main CPU version 00001.00 Main CPU version checking. Secondary CPU version 00020.21 Secondary CPU version checking. Operating Mode Description Operating mode Behaviors LCD display The battery is charging using utility/AC input power. Standby mode Note: The battery is charging using PV energy.
Page 27
Battery is charged by PV energy and feed PV energy to grid. The battery is not charging. Utility charges battery and provides power to load. Output power from Line mode utility. Charger Utility and battery power provide power to load. available PV energy, battery power and utility provide power to load.
Page 28
PV energy and the battery are supplying power to the loads. PV energy is charging the battery and providing power to the loads. Output power from Battery mode battery or PV The battery is providing power to the loads. PV energy is providing power to the loads. Only PV mode Output power from PV The battery is not charging.
Parallel Function 1. Introduction This inverter can be used in parallel in only split phase systems. A maximum of nine units can parallel together. The supported maximum output power is 54kW/54KVA. *If you want to use only one breaker at the battery side for the whole system, the rating of the breaker should be X times current of 1 unit.
Page 30
Three inverters in parallel: Power Connection Communication Connection Four inverters in parallel: Power Connection Communication Connection...
Page 31
Five inverters in parallel: Power Connection Communication Connection Six inverters in parallel: Power Connection Communication Connection...
Page 32
Seven inverters in parallel: Power Connection Communication Connection Eight inverters in parallel: Power Connection Communication Connection Nine inverters in parallel: Power Connection Communication Connection...
Page 33
3. LCD Setting and Display Setting Program: Program Description Selectable option Single: When selected, the unit is used in single AC output mode operation. *This setting is only available when the Parallel: When selected, this inverter is operated in parallel system. The maximum number of inverter is in standby parallel units is 9.
BMS Communication Install – EG4-LL 1. Introduction When connecting to an EG4-LL battery use the supplied RJ45 battery communication cable. Please check with your dealer or installer for details. This custom-made RJ45 communication cable delivers information and signal between lithium battery and the inverter.
Page 35
Battery Communication Install - EG4-LL Cont. Using the 1ft RS485 cable, interconnect the batteries as illustrated in the diagram below.
Page 36
Battery Communication Install – LiFePower4 Using the 1ft RS485 cable, interconnect the batteries as illustrated in the diagram below.
Page 37
For EG4-LL ensure the red power switch is set to "ON" as well as the breaker. Even with the EG4 batteries having built-in breakers, a minimum 150A in line breaker is required, and a 200A in line breaker is recommended.
Battery Based Commissioning REQUIRED PROCEDURE Note: Systems must be commissioned while connected to a battery bank. PV or AC input only based commissioning is not recommended or supported. NOTE: This guide is to be used after the physical installation of the system is complete. NOTE: For best use case, ensure that all settings are programmed per user/site specific requirements.
Page 39
Battery Based Commissioning REQUIRED PROCEDURE Cont. Multi-unit Systems: Step 1 - Ensure all inverter connections are correct, and all input and output breakers of the system are off. Step 2 - Turn on the system's DC breaker (between inverters and batteries if equipped), master battery breaker and/or power button, and then power on all inverters by depressing the power buttons (in that exact order).
Warning Indicator Warning Code Warning Event Icon flashing Fan locked Over temperature Battery over charged Low battery Overload Inverter power derating PV is weak Battery is not connected DSP remote command loss BMS disable charge/discharge BMS command loss BMS pack warning BMS stopped charge BMS force charge BMS stopped discharge...
Page 41
Faults Reference Code Fault Code Fault Event Icon on Fan is locked. Over temperature Battery voltage is too high. Battery voltage is too low. Output is short circuited. Output voltage is abnormal. Overload time out. Bus voltage is too high. Bus soft start failure.
Page 42
Problem LCD/LED/Buzzer Explanation / Possible cause What to do Unit shuts down LCD/LEDs and buzzer automatically will be active for 3 The battery voltage is too low 1. Re-charge battery. during startup seconds and then (<1.91V/Cell) 2. Replace battery. process. complete off.
Page 43
Situation Fault Solution Fault Event Description Code Restart the inverter. Check if L1/L2/N cables are phased properly in all inverters. Current feedback into For parallel system in split phase, make sure the red/black current the inverter is detected. sharing cables are connected well (with screws) to all inverters. If the problem remains, please contact your installer.
Wi-Fi Operation Guide in Remote Panel 1. Introduction The Wi-Fi module can enable wireless communication between off-grid inverters and the cloud monitoring platform. Users have complete and remote monitoring and control experience for inverters when combining the Wi-Fi module with the SolarPower APP, available for both iOS and Android based device. All data loggers and parameters are saved in the the cloud.
Page 45
Then, a “Registration success” window will pop up. Tap “Go now” to continue setting local Wi-Fi network connection. Step 2: Local Wi-Fi Module Configuration Now, you are in “Wi-Fi Config” page. There are detailed setup procedure listed in “How to connect?” section and you may follow it to connect Wi-Fi.
Page 46
Then, return to SolarPower APP and tap “ ” button when Wi-Fi module is connected successfully. Step 3: Wi-Fi Network settings icon to select your local Wi-Fi router name (to access the internet) and enter password. Step 4: Tap “Confirm” to complete the Wi-Fi configuration between the Wi-Fi module and the Internet. If the connection fails, please repeat Step 2 and 3.
Page 47
Diagnose Function If the module is not monitoring properly, please tap “ ” on the top right corner of the screen for further details. It will show repair suggestions. Please follow it to fix the problem. Then, repeat the steps in the chapter 4.2 to re-set network setting.
Page 48
Overview After login is successful, you can access the “Overview” page to have an overview of your monitoring devices, including overall operation situation and energy information for current power and daily power as below diagram. Devices Tap the icon (located on the bottom) to enter Device List page. You can review all devices here by adding or deleting Wi-Fi Module in this page.
Page 49
Part number label is pasted on the bottom of remote LCD panel. For more information about Device List, please refer to the section 2.4. User Information In ME page, users can modify “My information”, including User’s Photo , Account security , Modify password , Clear cache ,and Log-out , shown as below diagrams.
Page 50
Device Mode On the top of screen, there is a dynamic power flow chart to show live operation. It contains five icons to present PV power, inverter, load, utility and battery. Based on your inverter model status, there will be Standby Mode , Line Mode , Battery Mode .
Page 51
Swipe left Basic Information displays basic information of the inverter, including AC voltage, AC frequency, PV input voltage, Battery voltage, Battery capacity, Charging current, Output voltage, Output frequency, Output apparent power, Output active power and Load percent. Please slide up to see more basic information. Production Information displays Model type (Inverter type), Main CPU version and secondary CPU version.
Please refer to below parameter setting list for an overall description and note that the available parameters may vary depending on different models. Please always see the original product manual for detailed setting instructions. Parameter setting list: Item Description Output setting Output source To configure load power source priority.
Page 53
Record happens. Solar Supply Set solar power as priority to charge the battery or to power the load. Priority Reset PV If clicked, PV energy storage data will be reset. Energy Storage Start Time For The setting range of start charging time for AC charger is from 00:00 to Enable AC 23:00.