Sungrow SBR HV Battery Installation Quick Guide
Sungrow has released high-voltage battery - SBR series (9.6kWh-25.6kWh).
To ensure smooth installation and avoid difficulty on site, please read below checklists
and make sure you are ready before installing SBR HV batteries. If you have any
questions, please free to contact Sungrow team (1800 SUNGROW (786 476)
service@sungrowpower.com.au) before asking help onsite to reduce urgency.
Check Items
Requirements
Manuals
•
•
•
Application
•
Remote Support •
•
Remote Area
•
•
•
Internet
•
Cables/Tools
Prepare tools and cables prior to the installation.
•
•
•
•
Comm. Cable
•
Tips
•
GD_202106_Sungrow SBR HV Battery Installation Quick Guide_V1.0
As we continuously improving our services, changes to this document may occur without notice.
Read
Sungrow product manuals
Follow the manuals and make sure the operating environment is
suitable for inverter and batteries.
Check with the distributors or Sungrow team for technical advice of
off-grid application or any other complex scenarios (click here)
Battery parallel application will not be available by Q3 2021 and the
exact date is to be informed by Sungrow.
If it is the first installation of HV battery system, Sungrow advises
installers to book the time for remote support. Our team will deliver
support when you are on site to avoid any difficult to reach us.
Installers need to be cautious for the remote installation.
Installer must take responsibility of the after-sales service.
Sungrow technical support will be limited if the battery systems are
installed remote areas with no local electrician for service (click
for remote area policy)
The system needs to operate under internet available environment.
otherwise, Sungrow's support will be limited and less efficient.
If there is no Internet connection, please contact the distributors to
purchase 4G dongle for internet access.
DC power cables≥ 6mm
to Australia Standard.
Tools to make Ethernet cable with RJ45 terminal if the installation
requires COM cable longer than 3 meters.
The latest version of iSolarCloud is necessary to be installed on
mobile or tablet prior to the commissioning and firmware upgrading.
Long cables (>10 m) could cause communication failure between
the inverter and battery.
It's installer's responsibility to conduct communication cable
continuity test before contacting Sungrow team
Follow the installation tips & commissioning tips from the 2nd page
of this document