Inground luminaire

Advertisement

Phase One
Blockout Installation Procedure
(during earth or masonry work)
1) Ensure that proper drainage is provided for the
shown installation methods.
2) Ensure a suitable recess is provided to accommo-
date installation blockout/mounting ring assembly
B/M.
Warning: warranty void if luminaire installed with-
out appropriate drainage).
B/M in position and ensure that:
a) Arrow R on mounting ring M is pointed towards
the object to be illuminated (wall, tree, column).
b) Mounting ring M
appropriate gap.
c) Mains supply cable(s) O
connect sealable junction box J with cable E from
luminaire.
Ensure that installation blockout/mounting ring
assembly B/M is not damaged and has maintained
its original shape.
6) Framing should be installed to prevent vegetation
from growing over the lens.
Phase Two
Luminaire Installation and Electrical Connection
8) Check that rating shown on luminaire label conforms
with mains electrical supply.
mains supply cable O (for individual wiring) or
branch cable (for through wiring) in sealable junc-
tion box J – to connect cable(s). Follow the seal-
able junction box termination instruction included
in the packaging.
and sealable junction box J inside installation
blockout/mounting ring assembly B/M.
F. If the
For wallwash illumination only
Ensure the arrow indicated on the sticker is facing
11) Loosen countersunk screws C (do not turn out).
Insert mounting lever L between head of counter-
sunk screws C and cover lens. Place luminaire
D.
housing A into installation blockout/mounting ring
assembly B/M
mounting ring M.
Warning: When luminaire is placed inside installa-
tion blockout B, ensure there is no stress on seal-
able junction box J or electric cables (Fig. lll).
12) Tighten countersunk screws C 'hand-tight'.
4
E from luminaire housing A and
D
D on