4. Frame installation
※ Note 2. FRAME extension in horizontal direction
H LINK
H CENTER LINK
- Place FRAME H and FRAME V as extended installation specifications. (Fig.1)
- Insert HORIZONTAL LINK and H CENTER LINK into the extended connection area. (Fig.2)
(If extend the frame that has already been installed on the wall, it will be omitted. )
Fig.1
Fig.2