Installation
13
Gas installation
To be carried out by qualifi ed personnel
Mount a manual shutt-off valve prior to the dryer.
The gas pipe to the dryer must be dimensioned to an output
of 6.6 kW / 8 kW.
From factory the nozzle pressure setting corresponds to the
heating value printed on the data label on the back of the dryer.
Check that the nozzle pressure and heating value are according
to the values given in the table. If not, contact the supplier.
Bleed the pipe system before connecting the dryer.
After connection, test all joints for leaks.