Installation Tasks Checklist

To perform the actual switch installation, the site implementation engineer must perform the following
tasks, which are detailed in this section.
Be sure to review the Safety Information on page 1-9 before starting the installation and during the
Caution
installation process. Check the installation site to verify the installation of cabinet power feeds, rails, and
grounding.
Unpack the equipment and inspect for any shipping damage. Any shipping damage should be reported
Step 1
to the shipping company.
Step 2
Verify that the equipment shipped matches the packing list.
Mark the rack and install the mounting rails.
Step 3
Physically install the switch in the rack.
Step 4

Safety Information

The following safety guidelines are provided to ensure both personal safety for the user and to protect
the system from potential damage. These precautions cover the following categories:
Precautions fit into one of three categories:
A textual callout designed to emphasize:
Note
Potential for damage to system equipment. Damage to the system caused by the user may have potential
Caution
warranty implications.
Potential for personal injury.
Warning
Precautions for Rack-Mountable Products
Installing system components in a rack without the front and side stabilizers installed could cause
Warning
the rack to tip over. Therefore, always install the stabilizers before installing components in the rack.
OL-8787-05
Precautions for Rack-Mountable Products
Protecting Against Electrostatic Discharge
Electrical Safety Precautions
Tasks of particular importance.
Tips and reminders to maximize the use of the equipment.
Cisco SFS 7012 InfiniBand Server Switch Hardware Users Guide
1-9