11.
Mounting to Shop Floor
12.
Note: Re-check the bedway after 24 hours,
after two weeks, then annually to make sure
it remains level.
Mounting to Shop
Floor
Bolting to Concrete Floors
Figure 13
Figure 13
NOTICE
Anchor studs are stronger and more per-
manent alternatives to lag shield anchors;
however, they will stick out of the floor,
which may cause a tripping hazard if you
decide to move your machine.
Using Machine Mounts
Figure 14
NOTICE
We strongly recommend securing your
machine to the floor if it is hardwired to the
power source. Consult with your electrician
to ensure compliance with local codes.
NOTICE
The gap is installed, then ground at the fac-
tory during lathe assembly for precise fit
and alignment. Factors during the assembly
apply additional forces to the gap, making
replacing the gap to the original position
very difficult. If you choose to remove the
gap, we DO NOT recommend replacing it.
Figure 14