Download Print this page

Keysight N5241AU-944 Installation Notes page 27

Add 4-port capability upgrade kit

Advertisement

Step 18.Install the Bulkhead Connectors in the Test Set Front Plate
Refer to
Figure 12
for this procedure. New parts are listed in
1. If your analyzer's serial number is MY/SG/US5321 and above:
Locate the bulkhead connectors you removed earlier from the 2-port test set front plate of the
PNA. Use these and the new bulkhead connectors included in the kit for the remainder of this
step.
2. From the back side of the test set front plate, insert a bulkhead connector into a hole in the
plate.
3. Install 1x washer and 1x nut. Hand tighten nut and ensure bulkhead connector hexagon nut,
on the back side of test set front plate, is aligned to the test set subpanel hexagon indent.
4. Repeat previous two steps for the remaining bulkhead connectors.
5. Torque nuts, on the front side of test set front plate, to 21 in-lbs.
Figure 12
Bulkhead Connectors Installation
Installation Note N5242-90017
Installation Procedure for the Upgrade
Table 1 on page
7.
26

Advertisement

loading

This manual is also suitable for:

N5242au-944N5249au-944N5242-60109