Tempstar F97CMN Installation, Start-Up, Operating And Service And Maintenance Instructions page 46

Modulating, high efficiency condensing gas furnace, 4-way multipoise
Table of Contents

Advertisement

F97CMN and G97CMN: Installation, Start-up, Operating and Service and Maintenance Instructions
termination elbows as shown in
For Ventilated Combustion Air Termination, See
19. Use appropriate methods to seal openings where combustion air
pipe and vent pipe pass through roof or sidewall.
Diameter
PVC Sch 40
1 1/2-in.
38-mm
2-in.
51-mm
2 1/2-in.
64-mm
3-in.
76-mm
4-in.
Optional Installation of the Vent Pipe
NOTE: DO NOT USE THIS TECHNIQUE FOR POLYPROPYLENE
VENTING SYSTEMS.
This option provides a disconnect point for the vent pipe. The vent pipe
must be cemented to the plastic vent pipe adapter to maintain a sealed
vestibule, see
Fig.
57.
VENT PIPE ADAPTER WITH GASKET
INSTALLED ON FURNACE. VENT
PIPE IS CUT FLUSH WITH TOP OF
ADAPTER. PRIME AND CEMENT VENT
PIPE TO ADAPTER. ALLOW TO DRY
BEFORE INSTALLING VENT COUPLING.
VENT PIPE FLUSH WITH ADAPTER
Fig. 57 – Optional Vent Pipe Flush with Adapter
1. Insert a length of vent pipe through the casing into the outlet of the
vent elbow.
2. Slide the plastic vent pipe adapter over the length of the vent pipe
down to the furnace casing. Mark the pipe where it is flush with the
outlet of the adapter.
3. Remove the pipe from the furnace and the adapter and cut off any
excess pipe.
4. Clean and prime the end of the pipe that is flush with the vent
adapter with a primer that is appropriate for the type of pipe being
used.
5. Re-insert the pipe through the casing into the vent elbow.
6. Tighten the clamp around the outlet of the vent elbow. Torque the
clamp to 15 lb-in.
7. Apply cement to the end of the pipe and to the inside of the plastic
vent adapter.
8. Slide the adapter over the vent pipe and align the screw holes in the
adapter with the dimples in the furnace casing.
9. Pilot drill 1/8-in. screw holes for the adapter in the casing and
secure the adapter to the furnace with sheet metal screws.
10. Loosen the clamps on the rubber vent coupling.
11. Slide the end of the coupling with notches in it over the standoffs in
the vent pipe adapter.
Manufacturer reserves the right to change, at any time, specifications and designs without notice and without obligations.
Fig.
38,
Fig. 43
and
Fig.
50.
Fig.
41.
Table 14 – Hanger Spacing
SDR 21 & 26
3-ft.
2 1/2-ft.
914-mm
762-mm
3-ft.
3-ft.
914-mm
914-mm
3 1/2-ft.
3-ft.
1067-mm
914-mm
3 1/2-ft.
3-ft.
1067-mm
914-mm
4-ft.
3 1/2-ft.
ALIGN NOTCHES IN VENT PIPE
COUPLING OVER STAND-OFF
ON ADAPTER. TORQUE LOWER
CLAMP 15 LB-IN. WHEN REMAINING
VENT PIPE IS INSTALLED, TORQUE
UPPER CLAMP TO 15 LB-IN.
VENT PIPE FLUSH SHOWING COUPLING
CARBON MONOXIDE POISONING HAZARD
Failure to follow this warning could result in personal injury or death.
DO NOT use cement to join polypropylene venting systems. Follow
the polypropylene venting system manufacturer's instructions for
installing polypropylene venting systems.
Material
ABS
3-ft.
914-mm
3-ft.
914-mm
3 1/2-ft.
1067-mm
3 1/2-ft.
1067-mm
4-ft.
12. Tighten the clamp of the coupling over the vent pipe adapter.
Torque the lower clamp around the vent pipe adapter to 15 lb-in.
13. Pilot drill a 1/8-in. hole in the combustion air pipe adapter.
14. Complete the vent and combustion air pipe as shown in "Install the
Vent and Combustion Air Pipe."
FOR POLYPROPYLENE VENTING SYSTEMS
When using polypropylene venting systems, all venting materials used,
including the vent terminations, must be from the same manufacturer.
Installing the Vent Termination
Roof Terminations
A roof termination of any type will require a 4-in. (102 mm) flashing for
a 2 inch (50 mm ND) concentric vent or a 5-in. diameter (127 mm)
flashing for a 3-inch (80 mm ND) concentric vent kit. For two-pipe or
single pipe vent systems, a flashing for each pipe of the required
A13076
diameter will be necessary.
It is recommended that the flashing be installed by a roofer or competent
professional prior to installing the concentric vent. The terminations can
be installed on a flat or pitched roof.
Concentric Vent
Single or multiple concentric vent must be installed as shown in
Maintain the required separation distance between vents or pairs of vents
as shown in
Fig. 38
and all clearance shown in
NOTE: Follow the instructions of the vent terminal manufacturer. These
instructions are provided as a reference, only.
Cut one 4-in. (102 mm) diameter hole for 2-in. (50 mm ND) kit, or one
5-in. (127 mm) diameter hole for 3-in. (80 mm ND) kit in the desired
location.
Loosely
assemble
components together using instructions in kit.
Slide assembled kit with rain shield REMOVED through hole in wall or
roof flashing.
NOTE: Do not allow insulation or other materials to accumulate inside
of pipe assembly when installing it through hole.
Disassemble loose pipe fittings. Clean and cement using same
procedures as used for system piping. DO NOT CEMENT
POLYPROPYLENE FITTINGS.
46
WARNING
!
CPVC
Polypropylene
3-ft.
914-mm
3-ft.
914-mm
3 1/2-ft.
1067-mm
3 1/2-ft.
1067-mm
4-ft.
NOTICE
!
Fig.
43.
concentric
vent/combustion
3.25-ft.
1000 mm
3.25-ft.
1000 mm
3.25-ft.
1000 mm
3.25-ft.
1000 mm
3.25-ft.
Fig.
38.