 Electrical Connection 
Only  full  qualified  and  experienced  electrical 
technicians  should  carry  out  electrical  installation, 
service and repair work. 
 
Warning: 
!  Make  electrical  connections  in  compliance  with 
relevant  electrical  codes,  standards  or  other 
requirements. 
 
2.10.1 
Cabling 
Due  to  movement  of  generating  sets  on  their 
vibration mounts, the electrical connection to the set 
should  be  made  with  flexible  cable.  The  cable  must 
be  suitable  for  the  output  voltage  of  the  generating 
set  and  the  rated  current  of  the  set.  In  determining 
the  size,  allowances  should  be  made  for  ambient 
temperature.  Method  of  installation,  proximity  of 
other cables, etc. All connections should be carefully 
checked for integrity. 
Current carrying capacity of power cables that will be 
given  in  APPENDIX  A.  On  the  other  hand,  there  is  a 
one more important point while cable cross sections 
are being selected. If the distance between load and 
generator  is  too  length,  voltage  falling  at  the  load 
side  can  be  too  much  at  the  transient  current 
duration.  The  voltage  drop  across  a  cable  can  be 
determined as follows: 
3
L
I
Rcos
ΔU
1000
ΔU    Voltage drop (V) 
L      Length of conductors (m) 
I      Rated current (A) 
R    Resistance (Ω/km to VDE 0102) 
X    Reactance (Ω/km to VDE 0102) 
 
Refer to APPENDIX E Cable Current load standard. 
2.10.2
 Grounding / Earthing Requirements 
The  frame  of  the  generating  set  must  be  connected 
to  an  earth  ground.  Since  the  set  is  mounted  on 
vibration  isolators,  the  ground  connection  must  be 
flexible  to  avoid  possible  breakage  due  to  vibration. 
Ground  connection  cables  or  straps  should  have  at 
least  full  load  current  carrying  capacity  and  meet 
applicable regulations. 
 
2.10.3
 Insulation Test 
Before  starting  the  generating  set  after  installation, 
test  the  insulation  resistance  of  the  windings.  The 
Automatic  Voltage  Regulator  (AVR)  should  be 
disconnected  and  the  rotating  diodes  either  shorted 
Xsin
)
 
out  with  temporary  links  or  disconnected.  Any 
control wiring must also be disconnected. 
A 500 V Megger or similar instrument should be used. 
Disconnect  any  earthing  conductor  connected 
between  neutral  and  earth  and  megger  an  output 
terminal to earth. 
The insulation resistance should be in excess of 1MΩ 
to earth. Should the insulation resistance be less than 
1MΩ winding must be dried out. 
2.11
 Power distribution system 
Our diesel engine generator set use three phase five 
line  system  for  power  distribution.  That  is,  three 
phase  live  wires,  one  neutral  line,  one  ground  line. 
The  neutral  line  and  the  ground  line  are  not 
connected.  Users  can  choose  three  phase  four  lines 
for power distribution according to requirement that 
is  to  connect  the  neutral  line  to  the  ground  (base 
frame), so that to solve the problem of feint that the 
neutral line sometimes is electriferous.   
 
Note: 
HYUNDAI  Power  series  diesel  engine  generator  sets 
require  users  to  safely  connect  generator  sets  and 
base frames to the ground, please refer to the ground 
label for connecting point. 
11
User manual

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Dhy16kseDhy11kseDhy34kseDhy14kse

Table of Contents