UPS commissioning procedures
(Standard product, single UPS)
Preliminary and mechanical checks
After unpacking and placing of the UPS, verify for any
mechanical damage. Do never try to startup a damaged
UPS.
Make sure to maintain a minimum clearance of 10cm of the
UPS's lateral parts, for adequate ventilation with UPS's on
wheels.
Without wheels, in case of maintenance, a minimum
clearance of 50cm (20 inches) must be maintained !!)
Remove the Frontpanel and open the Frontdoor. Loosen the
3 screws on each side of the Sidepanes, to take them off.
See page UPS cabinet.
Before making any connections we recommand a thorough
mechanical check, including verification of loose bolts or
components, correct inserted plugs and no loose wires or
cables. Make sure fans spin freely.
If any problems with this installation are found that pose a
threat to persons or equipment, do not proceed until the
!!!
problem has been corrected

Installation

Connect Input and Output cables and fix them with the
enclosed cable ties.
Insure for adequate size of cables, (see table) and verify for
correct phase rotation.
Replace all the previously removed panels.
Verify for Q1 and Q2 to be open.
Open Mains Rectifier fuses, F1, F2, F3.
Open Battery fuses F9, F10, F11 !!