Conformity and standards ..............23 7 Commissioning ..............11 Checking the requirements for commissioning ....... 11 Servitec 35-95 with Touch controller 15.12.2021 - Rev. D Setting the minimum operating pressure for Magcontrol ....12 2 — English Servitec 35-95 with Touch controller — 01.04.2022...
Note! Reflex Winkelmann GmbH accepts no liability for any damage resulting from This symbol, in combination with the signal word 'Note', indicates useful failure to observe the information in this operating manual. In addition to the tips and recommendations for efficient handling of the product.
Control Touch controller 2-way motor control valve "CD" upstream of vacuum spray tube 2-way motor control valve "WV" upstream of vacuum spray tube Ball control ball valve "PV" downstream of pump "PU" 4 — English Servitec 35-95 with Touch controller — 01.04.2022...
Sequence of a degassing cycle in the vacuum spray pipe "VT" Example: Cooling water system ≤ 30 °C, System pressure 1.8 bar, "DC" system degassing in operation, "WC" make-up degassing closed. Servitec 35-95 with Touch controller — 01.04.2022 English — 5...
If necessary, provide support structures for the pipes or equipment. using the installation, start-up and maintenance certificate. This action is a prerequisite for the making of warranty claims. – Have the Reflex Customer Service carry out commissioning and ATTENTION the annual maintenance. Property damage caused by leaks...
For a water make-up via a "BT" mains disconnect receptacle, its bottom edge must be at least 1000 mm above the "PU" degassing pump. "SV" safety valve Various Reflex make-up variants, see chapter 4.6 "Optional equipment and "EC" expansion line accessories" on page 6 .
Before you remove the covers, "LIS" pressure pick-up completely isolate the device controller from the power supply. Verify that Pressure-maintaining station (compressor-controlled) with the main circuit board is voltage-free. expansion vessel Servitec 35-95 with Touch controller — 01.04.2022 English — 9...
Analogue input "PIS" pressure measuring. Voltage supply. Factory – For pressure Pre-wired AE (brown) indication and make- up with the Shielding (black) "Magcontrol" setting. WV make-up valve Pre-wired +24 V (supply) 10 — English Servitec 35-95 with Touch controller — 01.04.2022...
This action is GND S1 a prerequisite for the making of warranty claims. – Have the Reflex Customer Service carry out commissioning and RS-485 interface. the annual maintenance. User supplied S2 modules: Extension or communication module.
Displays general The calculation of the minimum operating pressure can be directly calculated information. and saved during initial commissioning using the Reflex Control Smart app for configuration. Please always check the correct inlet pressure of the expansion Calibrating the touch screen vessel in the system.
Do not yet switch to Automatic mode. Select the required Make-up variant and conform your entry with "OK". – For calculation of the make-up variant, see chapter 6.4 "Switching and make-up variants" on page 9 . Servitec 35-95 with Touch controller — 01.04.2022 English — 13...
Do not fully unscrew the venting screw. Wait until air-free water appears. – For Manual mode, see chapter 9.1.2 "Manual mode" on page 15 . Repeat the venting process until the "PU" pump is fully vented. Touch "Open" in Manual mode. 14 — English Servitec 35-95 with Touch controller — 01.04.2022...
10.1.4 Note! "Degassing programmes – overview" on page 18 . Filling the system with water is not part of the deliverables of the Reflex • Continuous degassing. Customer Service. •...
Pump damage may occur when the pump starts up if you turn the pump motor at the impeller using a screwdriver. • Switch the pump to a zero-volts state before turning the pump at the fan wheel with a screwdriver. 16 — English Servitec 35-95 with Touch controller — 01.04.2022...
Floating contact • Message selection > This menu is protected with a password. It can be accessed only by the Reflex • Message selection: only messages marked with "√" Customer Service. A partial summary of the settings stored in the Service menu are output.
Automatic activation occurs at every water make-up. – Make-up degassing is deactivated. • During continuous degassing. • Confirm your selection with "OK". • During interval degassing. Continuous degassing is activated. • Times: 18 — English Servitec 35-95 with Touch controller — 01.04.2022...
Seal the leakage in the system. Pressure Controller receives incorrect signal. • Check/connect the plug connection at the pressure "OK" measurement transmitter. • Check the cable for damage. • Check the pressure sensor. Servitec 35-95 with Touch controller — 01.04.2022 English — 19...
Page 20
Check the set values. – • Check the bus module. Outside operating Operating range exceeded. – • Lower the system pressure. range • Check ball valves on pump discharge side. 20 — English Servitec 35-95 with Touch controller — 01.04.2022...
• Control of the mixing ratio. • If necessary, adjust according Note! to manufacturer information. The gas must be eliminated from the device before the next interval starts. Servitec 35-95 with Touch controller — 01.04.2022 English — 21...
Ensure that installation work for the electric connection of the device is carried out by an electrician, and in compliance with electrical 11.4 Maintenance certificate engineering regulations. All maintenance tasks have been completed according to the Reflex Installation, Operating and Maintenance Manual. CAUTION Risk of burns Date...
Annex 13.3 Conformity and standards 13.1 Reflex Customer Service Device conformity declarations are available on the Reflex homepage. Central customer service www.reflex-winkelmann.com/konformitaetserklaerungen Central telephone number: +49 (0)2382 7069 - 0 Alternatively, scan the QR code: Customer Service extension: +49 (0)2382 7069 - 9505 Fax: +49 (0)2382 7069 - 9523 E-mail: service@reflex.de...
Need help?
Do you have a question about the Servitec 35-95 and is the answer not in the manual?
Questions and answers