Section Assembly - BAC PCT Cooling Tower Rigging & Assembly Instructions

Table of Contents

Advertisement

H1
Figure 1. Lifting basin section

Section Assembly

1. Remove any motors or accessories shipped in the cold water basin.
2. Figures 1 and 2 show the proper rigging of the sections for units
that ship in two sections. Position the lower section on the steel
support and bolt in place.
3. Using basin to casing joining brackets, guide the upper section
onto the lower section. Match marks must line up.
4. Fasten the hardware between the upper casing and lower section
per Figure 3a and 3b.
5. Seal the joint between the upper section and lower section as
described on page 6.
Casing Section being
lowered onto basin
Basin-to-Casing
Joining Bracket
Basin "Louvre"
Post
Figure 3a. Joining Casing to Basin section
Figure 3b. Joining Casing to Basin section
L
H2
Figure 2. Lifting casing/roofdeck section
Casing Section
lowered onto basin
Insert & tighten
bolts with sealer
washer to "lock"
casing to basin
See fig.3b
for detail
Unit Rigging & Assembly