Unit Weights
Before rigging any unit, the weight of each section should be verified
from the unit submittal drawing. Unit print weights include the final
assembled tower with all accessories.
Anchoring
Holes suited for M16 bolts are provided for bolting the unit to the
support beams. Refer to the suggested support drawing included in
the submittal for location and quantity of the mounting holes. The unit
must be level for proper operation. Anchor bolts must be provided by
others.
Support beams must also be level. Each footing should be shimmed
with a firm material to ensure the weight of the tower is carried at all
points and that the basin ledges are level at all places. Shims may be
required either side of a joint. This is to be done before the basin is
filled with water. If vibration isolators are used, a supporting framework
must be provided between the unit and the vibration isolators to
provide continuous and rigid support. Anchor bolts, footings and beams
to be supplied by others.

Cold Weather Operation

These products must be protected by mechanical and operational
methods against damage and/or reduced effectiveness during sub-
freezing temperatures. Please contact your local BAC Representative
for recommended cold weather operation strategies.

Location

All evaporative cooling equipment must be located to ensure an
adequate supply of fresh air to the fans. When units are located
adjacent to walls or in enclosures, care must be taken to ensure the
warm, saturated, discharge air is not deflected and recirculated back to
the air intakes.
Each unit must be located and positioned to prevent the introduction
of discharge air into the ventilation systems of the building on
which the unit is located and of adjacent buildings. For detailed
recommendation on BAC equipment layout, please contact your local
BAC Representative.

Warranties

Please refer to the Limitation of Warranties (located in the submittal
package) applicable to and in effect at the time of the sale/purchase of
these products.

Unit Operation

Prior to start-up and unit operation, refer to the PCT Operation &
Maintenance Manual shipped with the unit.
Introduction
Safety
Shipping
Pre-Rigging Checks
Unit Weights
Anchoring
Cold Weather Operation
Location
Warranties
Unit Operation
ATTENTION: Before an actual
lift is undertaken, ensure no
water, snow, ice, or debris
has collected in the basin
or elsewhere in the unit.
Such accumulations will
add substantially to the
equipment's lifting weight.