Step 5 - Connect Loads (equipment to be powered)
Load voltage is marked on the charger ratings label.
Load connections are to the terminal blocks in the DC Output Box.
Load terminal block (TB) is behind the Battery terminal block.
Each TB position is marked with its connection: BAT1+, BAT1-, BAT2+, BAT2-, 125V DC+, 125V DC-, 24VDC+, 24VDC
-, 48VDC+, 48VDC-.
1. Verify that equipment being powered accepts the charger output voltage.
2. Verify all DC breakers (DC1, DC2) are OFF.
3. Remove the DC Output Box cover - 4 thumbscrews.
4. Connect Load 1 Positive cable to the Positive terminal block position marked Load 1.
5. Connect Load 1 Negative cable to the Negative terminal block position behind the positive position marked
Load 1.
6. If DC2 Breaker is labeled "Load", Repeat from 4. for Load 2.
7. Replace the DC Output Box cover - 4 thumbscrews.
Battery TB
Screws
with 2 DC Load breakers
Page 12
© 2021 ABB. All rights reserved.
Bottom Feed
(Shown as 125VDC)
LOAD1+
Load TB
Behind
Battery TB
Top Feed
with 1 DC Load breaker
LOAD1–
Screws
Battery TB
Version 6.0

Advertisement

Table of Contents
loading

This manual is also suitable for:

8600092587p

Table of Contents