LTPH-SM-1014-03, Issue 3
B
Y
EFORE
Prior to installing the Wideband 3190, it is important to prepare for the installation by
•
Reviewing installation plans through establishing a Method of Procedure
•
Unpacking and inspecting the system components, and
•
Gathering the tools for the installation
R
I
EVIEWING
NSTALLATION
Installation personnel, engineers, and Central Office (CO) supervisors, involved in the installation of the
HMS-358, should participate in the preparation of a Method of Procedure (MOP) for approval by CO
management.
E
STABLISHING A
Following is a list of tasks and considerations that need to be addressed and mutually agreed upon before
proceeding with installation:
•
Assignment of personnel
•
Installation tools and methods
•
Protection requirements for personnel, equipment, and tools
•
Evaluation of potential hazards that may affect service
•
Scheduled time for installation
•
Space requirements (see
•
Power requirements (see
•
Identification of procedures and tests required before connecting to working equipment
•
Identification of work steps and any necessary notifications to CO personnel or engineers before work begins
•
Assignment of individual system IDs for up to 32 managed systems
(see
"Setting the Shelf Identifier (Option D)" on page
•
Assignment of IP addresses for each installed system
(see
"Setting the Local IP Address (Option A)" on page
HMS-358 List 1 and List 2
B
OU
EGIN
P
LANS
M
P
ETHOD OF
"Power Requirements" on page
"Power Requirements" on page
January 12, 2001
ROCEDURE
88)
88)
35)
36)
Before You Begin
3