29 to 33 Plate
1. Install "L" connector with vertical bolt as below. Bolts
should be installed loosely for future adjustments. Duplicate
connection process at both connection points.
2. Install "C" connector to cell post using horizontal bolt
as below. Bolt should be installed loosely for future
adjustments. Duplicate connection process at both
connection points.
3. Ensure proper alignment of connectors to cell posts.
4. Tighten & torque the horizontal bolt to 125 in-lb prior to
tightening and torqueing the vertical bolts in step 1.
NOTE: For this connection point it is acceptable to torque
the head of the bolt.
Terminal Assembly
Top Termination
Consult battery string layout diagram for termination location.
1. Remove module bolt directly behind terminal plate location. If
location contained safety shield bracket assembly install cap
washer in front of dragon tooth washer and re-install safety
shield bracket assembly Install plastic cap after bolts are
torqued. Consult "Hardware Torque Requirements" (pg b.4)
for proper torque values.
2. Install terminal plate bracket to the top of the module. Use
3/8-16 x 1.25" hardware. Install loosely for future alignment.