Pre-Start

Upon completion of installation, complete the Sintesis™
RTAF Installation Completion Check Sheet and Request
for Trane Service checklist in chapter
Sheets," p.
98.
Important:
Start-up must be performed by Trane or an
agent of Trane specifically authorized to
perform start-up and warranty of Trane
products. Contractor shall provide Trane (or
an agent of Trane specifically authorized to
perform start-up) with notice of the
scheduled start-up at least two weeks prior
to the scheduled start-up.
RTAF-SVX001K-EN
"Log and Check
57