2. MAINTENANCE PROCEDURES

2.1 General Information

!
In order to ensure the safety of the patient and the operator, the unit should undergo an inspection
and test after 800 hours of use or every 6 months, whichever comes first. The inspection and test require a
specific knowledge of the unit, and therefore have to be made by specially trained SIARE authorized
personnel.
The anesthetist or doctor is responsible for the ordinary maintenance of the unit, as described in this chapter.
Cleaning, disinfecting, sterilization and replacement of parts should be done as per the instructions in the
user's manual in order to avoid damage to the equipment that could also endanger the safety of the patient
and operator.
The components used have been selected after technical and comparative tests in the designing phase of
the machine.
Furthermore, the same components are always tested during the manufacturing cycle in order to obtain the
maximum level of safety and reliability for the operator and patient.
Therefore whenever a part needs to be replaced, it must be an original spare part, which has been checked
and tested by SIARE.
SIARE assumes responsibility for all provisions of the law, if the unit is used and maintained as per the
instructions in this manual and the technical manual. The Technical Assistance Report, signed by the
authorized SIARE technician, is proof of the completion of the scheduled maintenance.
P.N.: DU5506130