Entes EVM-R3 Instructions

Entes EVM-R3 Instructions

Rail mounted digital voltmeter

Advertisement

Quick Links

RAIL MOUNTED DIGITAL VOLTMETER
EVM-R3 / EVM-R3C / EVM-R3S

Precautions For Installation and Safe Use

No responsibility is assured by the manufacturer or any of its
subsidiaries for any consequences arising out of the use of this
material.
EVM-R3 (Digital Voltmeter) :
EVM-R3S (3-Phase Digital Voltmeter) :
EVM-R3C (Setpointed Voltmeter) :
Minimum and Maximum Voltage :
Setpoint (SP):
Latch Function ( ):
At position “0”:
At position “1”:
Instant Tripping
:
p
At position ‘‘0’’:
At position ‘‘1’’:

Setting of Set Point Value (For EVM-R3C)

set
up
down
set
up
down
down
set

Setting of Delay Time (For EVM-R3C)

set
up
down
set
up
down
set
All manuals and user guides at all-guides.com
s p
s p
SP
2 5 0
2 7 5
up
s p
dt
10.0
up
down
15.2

Setting Latch Function (For EVM-R3C)

set
up
down
set
up
down
set

Setting Instant Tripping Function (For EVM-R3C)

set
up
down
set
up
down
set

Displaying and Deleting Tripping Number (For EVM-R3C)

set
up
down
set
Press up button to delete tripping
number, else do not press any button.
set

Adjustment Contact Situation (For EVM-R3C)

set
up
down
set
up
down
set

Escaping the Set Menu (For EVM-R3C)

up
down
set

Displaying Phase-Phase or Phase-Neutral Voltage (For EVM-R3S)

desired voltage
L1-N
L2-N
L3-N
s p
lt
0
i
s p
tP
p
i
0
s p
OP
0 p
0 0 5
0 0 0
s p
CO
0
0 0 0
e s c
ESC
0 0 0
L1-L2
L2-L3
L1-L3

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the EVM-R3 and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for Entes EVM-R3

  • Page 1 All manuals and user guides at all-guides.com RAIL MOUNTED DIGITAL VOLTMETER EVM-R3 / EVM-R3C / EVM-R3S Precautions For Installation and Safe Use Setting Latch Function (For EVM-R3C) down down No responsibility is assured by the manufacturer or any of its subsidiaries for any consequences arising out of the use of this material.
  • Page 2 All manuals and user guides at all-guides.com RAIL MOUNTED DIGITAL VOLTMETER EVM-R3 / EVM-R3C / EVM-R3S Technical Data Displaying Minimum Voltage (For EVM-R3C) down Displaying Minimum Voltage (For EVM-R3) Displaying Maximum Voltage (For EVM-R3C) Displaying Maximum Voltage (For EVM-R3) Deleting the Minimum and Maximum Voltages...

This manual is also suitable for:

Evm-r3cEvm-r3s

Table of Contents