Indoor Unit Drain Piping

- Drain piping must have down-slope (1/50 to
1/100): be sure not to provide up-and-down
slope to prevent reversal flow.
- During drain piping connection, be careful
not to exert extra force on the drain port on
the indoor unit.
- The outside diameter of the drain connection
on the indoor unit is 32 mm.
Piping material: Polyvinyl chloride pipe VP-25
and pipe fittings
- Be sure to execute heat insulation on the
drain piping.
- Install the drain raising pipes at a right
angle to the indoor unit and no more than
300 mm from the unit.
Pipe clamp
Indoor unit
Maintenance
drain port
Heat insulation material: Polyethylene foam
with thickness more than 8 mm.

Drain test

- Connect the main drain pipe to the exterior
and leave it provisionally until the test comes
to an end.
- Feed water to the flexible drain hose and
check the piping for leakage.
- When the test is complete, connect the
flexible drain hose to the drain port on the
indoor unit.
Feed water
Upward
routing
1
Remove the Air Filter.
not allowed
Air outlet vents
2
Check the drainage.
- Spray one or two glasses of water upon
the evaporator.
- Ensure that water flows drain hose of
indoor unit without any leakage.
INSTALLATION OF INDOOR
Flexible drain hose
(accessory)
Main
drain pipe
Glue the joint
Air filters
9

Advertisement