UPS5000-H-(1200 kVA-1600 kVA) Quick Guide (100 kVA Power Modules, Three-Phase Three-Wire)
Installing Copper Bars and Signal Cables inside the UPS Cabinet
Remove parallel copper bars.
Install screws on battery
copper bars at the
combination position.
Remove the screws
preinstalled on
copper bars and
install parallel
copper bars.
Installing Power Cables between the UPS and the Inductor Cabinet (1600 kVA)
Copper bars are heavy. Two persons are required.
•
Cables have been preinstalled and bound in the inductor cabinet.
The cables from the inductor cabinet to the UPS are configured based on the longest cable
•
Install screws on
length before delivery. If short cables are needed in the actual installation scenario, you can
output copper bars
cut the excess cables and crimp terminals.
at the combination
Cables must be bound to the nearest beam or cable bridge according to the route shown in
•
position.
the figure.
•
Do not bind signal cables and power cables together.
The number and colors of cables in the figures are for reference only.
•
Power cable hole
Signal cable hole
Cable
Position of Wiring Terminal 1
Cabinet
Port
Cable 1 Power cabinet 1 PU XS1
Cable 2 Power cabinet 1 Signal
Cable 3 Power cabinet 1 One end of the NTC cable and inductor
cable is preinstalled. The other end is
Cable 4 Inductor cabinet
reserved inside the cabinet and needs to
be connected to the bypass cabinet.
Single Power Source
Different Power Sources
Position of Wiring Terminal 2
Cabinet
Port
Power cabinet 2
PU XS1
Power cabinet 2
Signal
Bypass cabinet
XS5
XS1
6
Side view of the UPS
Signal cable hole
Power cable hole
Side view of the UPS
Power cable hole
Signal cable hole