Shimadzu GCMS-QP2010 Service Manual
Hide thumbs Also See for GCMS-QP2010:

Advertisement

 
225-00612A
Gas Chromatograph Mass Spectrometer
GCMS-QP2010
Service Manual
1

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the GCMS-QP2010 and is the answer not in the manual?

Questions and answers

Summary of Contents for Shimadzu GCMS-QP2010

  • Page 1   225-00612A Gas Chromatograph Mass Spectrometer GCMS-QP2010 Service Manual...
  • Page 2 Safety Precautions Before starting work, read and fully understand the Danger, Warning, Caution, and Notes safety items in the yellow page at the beginning of the GCMS-QP2010 System User Guide (225-00822). The GCMS-QP2010 contains hot parts, such as the GC2010 heater unit, interface heater unit, and ion-source heater unit, a high-voltage power supply for the detector unit, and high-voltage circuits such as the vacuum-measurement circuit.
  • Page 3: Table Of Contents

      Contents CONTENTS........................... 3 1. INSTALLATION......................... 5 1. Checking Installation Conditions ................... 6 2. Unpacking, Assembly, Installation ................. 8 3. Environment Settings, Start-up..................11 4. Leak Check, Auto-tuning ..................... 13 5. Auto-tuning ........................15 6. Qualitative Analysis (SCAN Mode) ................16 7.
  • Page 4 1. Precautions during maintenance work ..............113 2. Adjustment in the high mass-number range .............. 114 3. Detailed explanation of CI and NCI ................107 4.Shimadzu Gas Chromatograph Mass Spectrometer ..........111 5.Installation Completion Checksheet ................114 6. How to change Turbopump ..................118...
  • Page 5: Installation

      1. Installation Day 1 1. Checking Installation Conditions 2. Unpacking, Assembly, Installation 3. Environment Settings, Start-up 4. Leak Check, Auto-tuning Day 2 5. Auto-tuning 6. Qualitative Analysis (SCAN Mode) Day 3 7. Quantitative Analysis (SIM Mode) 8. S/N Measurements(EI mode) Day 4 9.
  • Page 6   Day 1 1. Checking Installation Conditions Confirm the installation conditions, according to the Installation Completion Checksheet (ZEAV-0416). Check the power supply. 1)power requirements Frequency requirements MS power supply: 115V±5%, 1000VA                 230v±5%,1000VA GC power supply: 115V±5%, 1800VA 230V±5%,2600VA 230V±5%, 2600VA for high-power oven specification.
  • Page 7   4) Power cable connection The end of power cables for GC and MS constructed as shown below. Power cables for GC Black: Connected to the HOT side of AC line. White: Connected to the NEUTRAL side of AC line. GREEN: For grounding Power cable...
  • Page 8   Day 1 2. Unpacking, Assembly, Installation Unpacking The entire unit comes in six corrugated-fiberboard boxes: GC, MS, RP, PC, CRT, and printer. The GC unit weighs 30kg and the MS unit weighs 45kg. Take care to avoid accidents when unpacking these heavy boxes.
  • Page 9   limit of measurement. Turn on the main switch and confirm that the resistance across the power line and earth exceeds the limit of measurement. Other visual insulation checks Open the front door of the analysis tube and check that the filament heater and thermocouple are in the correct positions.
  • Page 10   Check the following points about the carrier gas connections. Carrier gas pressure The operational gas supply pressure to the GC is in the range 300 to 980kPa. But some supply pressures have a limiting effect on the pressures that can be set at the GC. The normal supply pressure is 700 to 800kPa.
  • Page 11 Select “Another Device”. Press [Next (N)]. Press [Use Disk]. Insert the CD-ROM Enter "E:¥Driver" and press [Enter]. Select “Shimadzu GCMS-QP2010”. Press [Next (N)]. Press [Next (N)]. Environment settings Set up the software environment, as described in section 3.3 System Configuration of the Operation Guide.
  • Page 12   Press [Manual] on the Start/Stop window to monitor the vacuum status and degree of vacuum. Go to Section 3 if problems occur!
  • Page 13: Auto-Tuning

      Day 1 4. Leak Check, Auto-tuning Leak check Check for air leaks with the instrument unheated, as described in section 4.2 Leak Check of the Operation Guide. □ Is m/z28 within twice m/z18? Set the temperature of the ion source, INJ, COL, and interface and repeat the check to ensure stability.
  • Page 14   Do not increase the ion source or interface temperature above the level required for analysis.
  • Page 15   Day 2 5. Auto-tuning Leak re-check Conduct a leak check to confirm that the air has reduced since the initial day. Confirm that m/z32 / m/z31 does not exceed 3 when SI(PFTBA) is inserted. Check for external abnormalities Look at the external appearance of the instrument and listen for noises to confirm no abnormalities are present.
  • Page 16: Qualitative Analysis (Scan Mode)

      Day 2 6. Qualitative Analysis (SCAN Mode) Describe the method of qualitative analysis using a standard sample, such as OFN 100pg/µL. Operation Description Explain the file types described in Section 2.9 Common Operations of the System User Guide and how to use Data Explorer, and create a new project folder. Explain the analysis method and data analysis method in accordance with section 6 Qualitative Analysis (SCAN Mode) of the Operation Guide.
  • Page 17   Conduct three measurements. Do not continue the measurements if the S/N is lower than the criteria. (After several dozen injections, waste from the septum can contaminate the insert, making S/N hard to measure.)
  • Page 18: Quantitative Analysis (Sim Mode)

      Day 3 7. Quantitative Analysis (SIM Mode) Describe the method of quantitative analysis using a standard sample, such as OFN 100pg/µL. Explain the analysis method and quantitation method in accordance with section 7. Quantitative analysis (SIM Mode) of the Operation Guide. Points to Explain to the Customer Principle of SIM, explanation of channels and groups How to create methods...
  • Page 19: S/N Measurements

      Day 3 8. S/N Measurements Measure S/N.(EI MODE) SAMPLE OFN 1pg/ul (isookutane solvent) 1ul Measurement Conditions 250 C SPLITLESS mode (sampling time 1.0 minute) COL: 50 C (1min) - 40 C / min - 200 C (0min) - 15 C / min - 280 C I/F: 250 C 200 C...
  • Page 20: Batch Processing, Report Printing, Qa/Qc

      Day 4 9. Batch Processing, Report Printing, QA/QC Describe continuous analysis using section 8. Batch Processing (Continuous Operation) of the Operation Guide. (Go through this description, even if the customer has no pretreatment unit or autosampler.) Points to Explain to the Customer How to create batch files (using Wizard) Describe the method of printing reports using section 9.Report Printing of the Operation Guide.
  • Page 21: Maintenance

      Day 4 10. Maintenance Describe the maintenance of the instrument using section 8.Maintenance of the Operation Guide. Points to Explain to the Customer Precautions to take during maintenance work Filament replacement procedure How to mount and dismount the ion source (Emphasize that the screws at the left must be tightened first when mounting the ion source.) How to conduct leak checks Maintenance of the INJ unit...
  • Page 22: S/N Measurements  Ci  Mode(Option

      Day 5 11. S/N Measurements  CI  MODE(OPTION)              Measure S/N.(CI MODE) Benzophenone 100pg/ul (acetone solvent) 1ul INJ: 250℃              SPLITLESS MODE (Sampling Time 2.0 min) COL:  80℃(2min)−30℃/min−260℃(5min) I/F:  250℃                    IS:200℃  during injection and analysis He: ...
  • Page 23: S/N Measurements  Nci  Mode(Option

      Day6 12.S/N Measurements  NCI  MODE(OPTION) Measure S/N.(NCI MODE) SAMPLE OFN 100fg/ul (isookutane solvent) 1ul Measurement Conditions 250 C SPLITLESS mode (sampling time 1.0 minute) COL: 50 C (1min) - 40 C / min - 200 C (0min) - 15 C / min - 280 C I/F: 250 C 200 C...
  • Page 24: Mass Patern Check Measurements  Di  Mode(Option

      Day 7 13.Mass patern check Measurements  DI  MODE(OPTION) cholestane 100ng/ul (acetone solvent) 1ul MS I/F 100℃ IS 250℃ DI temperature  room temperature to 300℃ (40 C / min) GC temperature constant Colum flow moderate flow...
  • Page 25: Maintenance

      2. Maintenance Daily Maintenance 1. MS Navigator Description of Parts 2. Instrument Configuration 3. Lens Unit 4. Interface Unit 5. Valves 6. MS Filter Unit 7. Detector Unit 8. Turbo Molecular Pump 9. Main Power Unit 10. GC unit Adjustment Software 11.
  • Page 26   Daily Maintenance 1. MS Navigator GCMSsolution incorporates the MS Navigator as a guide to normal daily maintenance. Follow the procedure below to use MS Navigator. 1. Run GCMSsolution (Analysis, Post-run, or Edit analysis) 2. In the Help (H) menu, select [Help Contents (C)]. 3.
  • Page 27  ...
  • Page 28   Description of Parts 2. Instrument Configuration COVERCPU 225-11016 225-11000-91 PCB ASSY CPU Screw、SUS screw washer M3×6 PCB ASSY MAIN CTRL-A 225-11130-91 Screw, SUS screw-washer, M3X6 020−46534 Screw、SUS Screw washer M3×6 Screw, SUS screw-washer, M3X6 Screw,SUS screw washer Screw, SUS screw-washer, M3X6 020−46534...
  • Page 29   Description of Parts 3. Lens Unit Lens fixing screws (2 positions) Ion-source lens unit removal procedure   1. Please remove, take a/ column. 2. Remove the ion-source box. 3. Slide the pipe at the tip of the interface to the left. The spring is held by the magnet; remove it carefully.
  • Page 30   Details of the lens unit 22 12 ⑪ IS MAG Base Assy 225-10440-91 29 29 ⑫ Heater Block 225-10439-91 ⑮ LENS 2 Assy 225-10263-91 15 28 29 ⑯ LENS 3 Assy 225-10264-91 ⑰ LENS 4 Assy 225-10265-91 16 ⑱ Spring Assy 225-10266-91 18...
  • Page 31   Description of Parts 4. Interface Unit O-ring 4DP105 036−11271 IF ASSY Screw, SUS screw-washer, M4 x 8 225-10525-91 -92 020-46547 BLIND PANEL 225-10281 Screw, SUS screw-washer, M4 x 12 020-46549 If it attach   ci or nci 020-46534 SUS Screw washer M3×6 、...
  • Page 32: Valves

      Description of Parts 5. Valves Standard Sample Inlet Unit VALVE Assy 225-10179-91 Capillary Assy 225-015559-91 Glass sample pin SI Assy 225-04257-91 225-10180-91 O-ring 036-11202 Leak Valve Leak valve Assy BRACKET,LEAK VALVE 225-10118 Bolt SUS with hole M3X6 LEAK VALVE ASSY 225-10116-91 BOLT WITH...
  • Page 33: Ms Filter Unit

      Description of Parts 6. MS Filter Unit MS filter removal procedure 1. Turn off the power. Disconnect the power connector. 2. Remove the DET Assy. (Remove three cables and four screws.) 3. Remove the rear panel. Remove the DIFF PCB unit cover. 4.
  • Page 34   Short spring Note : The short springs are inside the position shown in the diagram above. The distance of the springs from the insulators are as follows: Pre-rod end 17.5mm Detector end 21.5mm Removing the ROD Assy 1. Remove the three rod fixing screws. 2.
  • Page 35: Detector Unit

      Description of Parts 7. Detector Unit Detector (complete) Detector (electron multiplier 225-10463-91 only) 225-09340-11 DET(H)ASSY 225-10465-91 CDD electrode DET LENS Ion signal connector APERTUR PCB PRE AMP-A 225-11030-91 CDD/detector high-voltage power supply HV PCB ASSY 225-11195-91 OR HV PCB ASSY NCI 225-11195-92 During installation (or replacement), confirm that the signal connector pin, high-voltage connector pin, and detector fixing hooks are...
  • Page 36: Turbo Molecular Pump

      Description of Parts 8. Turbo Molecular Pump TMP fixing screws (4 positions) TMP2 (TW70) TMP1 (TW300) RP connection (TMP exhaust unit) Two turbo molecular pumps (TMP), one for the ion-source unit exhaust (TW-300) and one for the analyzer exhaust (TW-70), are connected to a single rotary pump (E2M1.5). Removing the Turbo Molecular Pumps 1.
  • Page 37: Main Power Unit

      Description of Parts 9. Main Power Unit Caution To prevent electric shocks, disconnect the power cable from the instrument before starting maintenance work on the main power unit. Power supply LEA150F-24 074-80424-01 Power supply LEA50F-5 074-80422-01 Power supply LEA50F-24 074-80422-51...
  • Page 38: Gc Unit

    After being used a few times, the ferrule can deform, causing leaks or damage to the column. same Vespel ferrules used GCMS-QP2010 at both the inj side and interface. 670-15003-03 for 0.25mm ID 670-15003-04 for 0.32mm ID 670-15003-05 for 0.53mm ID...
  • Page 39: Updating The Flash Rom

      Adjustment Software 11. Updating the Flash ROM A Flash ROM is mounted on the CPU-A PCB in the GCMS-QP2010. Follow the procedure below if a Flash ROM update is required. (The ROM version is displayed in the GCMSsolution System Configuration.) *Before updating the Flash ROM, stop the instrument (vacuum system) and exit GCMSsolution.
  • Page 40 7. Click the OK button if the ROM size and checksum values are correct. Alternatively, click the Cancel button to halt the update. 8. When the OK button is pressed, the ROM file is transferred to the GCMS-QP2010 and the update process starts. The progress status is displayed in the status display area.
  • Page 41   10. After writing to the Flash ROM is complete, the READY and FAILURE LED indicators flash 20 times simultaneously, the CPU is reset, and the instrument is rebooted. 11. If the instrument reboots normally after the reset is applied, a message indicating that the update is complete is displayed, as shown in Fig.
  • Page 42: Backing Up And Restoring The E2Prom

    12. Backing Up and Restoring the E2PROM * MS2010.EXE Version 1.20, or above An E2PROM mounted on the CPU-A PCB in the GCMS-QP2010 stores various parameters and times of consumable use. After CPU-A replacement, follow the procedure below to copy the E2PROM contents to the new PCB.
  • Page 43   Fig. 1-2 E2PROM Tool Window 2. Select "Backup" from the Process menu. Fig. 1-3 Backup Menu 2. The Save As dialog box opens. Select the directory and file name to be saved, and then click the Save button. The default file name is "instrument S/N.bin".
  • Page 44   Fig. 1-4 Save As Dialog Box 4. The following message is displayed when the E2PROM backup is complete. Fig. 1-5 Backup Complete Dialog Box Changing E2PROM Contents Use the Edit mode to change the contents of the E2PROM. Restoring the E2PROM Contents 1.
  • Page 45   2.Please do about the following contents before the work of the next 3 items. ① Select extend of the Process menu in E2PROM. ② Enter pass word. (MSALPHA) ③ Selsct Edit Mode. ④ Enter Serial No. (This work in, proper number, for example 12345 even good) ⑤...
  • Page 46   Cansel Fig. 2-3 Message Box to Confirm Restore 6. If the E2PROM is restored normally, close the window and reboot the instrument. Fig. 2-4 Restore Complete Dialog Box...
  • Page 47: Adjusting The Rf Ps Assy

      Adjustment Software 13. Adjusting the RF PS Assy Preadjustment 1. Run MS2010.EXE. Select the Profile Measurement tab. 2. Click the CONNECT button on the tool bar. 3. Check RF power supply tuning Select "RF Tuning" from the Tools menu. The RF Tuning window opens. Set the mass number and click on the RF ON button.
  • Page 48   7. Make coarse adjustment of the lens voltages (Lenses 1 to 4) to maximize the m/z=69 peak intensity. Adjust the detector voltage (EM) into the range 100000 to 200000. 8. Press the end measurement button when the adjustment is complete. Adjustment of RF power-supply trimmers VR1 (RF) and VR2 (M/Z) * Remove the rear cover before adjusting the RF power-supply trimmers.
  • Page 49   AC (52.5kHz) Adjustment 1. Select "Adjust 52.5kHz" from "Adjust Resolution" in the Tools menu. 2. The RF Power Supply AC Adjustment window opens. (Fig. 3) Signal strength Status display AC VALUE AC parameters RES VALUE Check Start button Check Adjust Check cancel Peak full width at half maximum(FWHM) Start button...
  • Page 50   3.3 RES Gain The peaks normally become fatter when AC is applied. The RES Gain parameter corrects for this effect. It is set during auto-tuning and does not need to be adjusted. 3.4 AC1, AC Coeff, RES Coeff Linear AC application is inadequate in the medium mass-number range when AC is first applied.
  • Page 51   4. Press the CHECK button to confirm the full width at half maximum (FWHM) for each peak and how AC is applied (peak separation and signal strength). At the start of this check, "CHECKING…" flashes green in the status display. The display reverts to "WAIT…"...
  • Page 52   4.2 Checking the medium mass-number range (169, 219) The medium mass-number range is adjusted using AC1, AC Coeff, and RES Coeff parameters. Fig. 4-3 Insufficient AC Fig. 4-4 Appropriate AC Fig. 4-5 Excess AC At m/z 219 and 169, the peak separation of isotopes deteriorates with insufficient AC, as shown in Fig.
  • Page 53: Troubleshooting

      3. Troubleshooting Problems when turning the power on 1. MS does not turn on 2. Abnormal Status LEDs Problems when running software 3. Cannot connect to MS 4. Cannot connect to GC Problems when starting evacuation 5. No ready status after automatic start 6.
  • Page 54   Problems when turning the power on 1. MS does not turn on Check the power supply. □ Is the power supply voltage within the required range for the MS? MS required voltage: 100V □ Is the power cable connected correctly? □...
  • Page 55   Problems when turning the power on 2. Abnormal Status LEDs Check the status of the LEDs when the power is turned on. □ Do the POWER (yellow) and FAILURE (red) LEDs remain lit? −−> CPU is not operational. Check the CPU-A power supply. Hint This symptom appears in the following circumstances: No 24V supply to the DC POWER PCB.
  • Page 56   Problems when running software 3. Cannot connect to MS Check the MS power supply. □ Is the power switch turned ON (1)? Hint Connection with the PC is not established for about 15 seconds after the MS power is turned on.
  • Page 57   Problems when running software 4. Cannot connect to GC Check the GC power supply. □ Is the GC power switch turned ON (1) ? Check the connector cable. □ Are the MS and GC connected correctly? The MS and GC are connected together with a 232C cable. Check the GC communications parameters.
  • Page 58   Problems when starting evacuation 5. No ready status after automatic start Check the GC settings. □ Is an appropriate carrier gas pressure set at the GC? An inappropriate carrier gas supply can result in no pressure increase at the column inlet, so that the automatic startup sequence does not begin (and the rotary pump does not operate).
  • Page 59   Hint It is sometimes possible to identify very large leaks by turning off the GC and MS and listening for them.
  • Page 60: No Ready Status After Automatic Start

    TMP power supply. Replace one of these and check the condition again. Caution The power supplies for the large TMP and small TMP are incompatible in early GCMS-QP2010 models. Never swap the wiring for testing purposes or normal operation will not be subsequently possible.
  • Page 61   (3) TMP ON Does the Pirani gauge drop below 100Pa within 5 minutes of turning on the turbo molecular pump (TMP)? No −−> error Does TMP become READY within 5 minutes? No −> error (4) Vacuum READY 30 seconds after both TMP become READY The FAILURE status LED flashes red if evacuation stops automatically for protection.
  • Page 62: Pirani Gauge, Ic Value Too High, Ig Does Not Light

      Problems when starting evacuation 6. Pirani gauge, IC value too high, IG does not light Check the column flow rate. □ Is the column flow rate within the recommended range? At a column flow rate of approximately 2mL/minute, the Pirani gauge value is about 40Pa or lower at the start of evacuation and about 1 to 10Pa after one day.
  • Page 63: Loud Noise

      Problems when starting evacuation 7. Loud noise Check the source of the noise. □ Source is RP? Oil deteriorated, worn rotor −> Replace oil, overhaul □ Source is TMP1? Defective bearing, wear, damaged blades −−> Replace TMP. □ Source is TMP2? Defective bearing, wear, damaged blades −−>...
  • Page 64: No Peaks Obtained (Peaks Extremely Small)

      Problems during tuning 8. No peaks obtained (peaks extremely small) Check the tuning file. □ Are the lens voltage values appropriate? Revert the lens voltages to the default values if unclear whether the tuning values are appropriate. The default values are as follows: L1 1.0V / L2 -20V / L3 -1.5V / L4 -40V / P-Rod -3.5V / M-Rod -3.5V / FIL-EV -70V / FIL-EM 60V / CDD -10000V / EM -900 ~ -1200V Check the introduction of PFTBA.
  • Page 65   Problems during tuning 8. No peaks obtained (peaks extremely small) (cont.) Check the ion source. □ Is the ion source correctly installed? Check if the ion source was distorted during installation. □ Is any foreign matter inside the ion source? Check inside the ion source for foreign matter, such as fragments of broken column.
  • Page 66   MAIN CTRL-A. A variety of causes could lead to lack of signal output or small signals. If the problem is not resolved by the checks above, check each electrical unit in the sequence below. Vacuum system Low degree of vacuum can lead to poor peak strength and unfamiliar peaks may appear. Filament In principle, defective control causes an error display.
  • Page 67: Ion-Source Temperature Does Not Rise Or Rises Too High

      Problems during tuning 9. Ion-source temperature does not rise or rises too high Check the heater switch. □ Is the heater switch in the ON position? The heater switch automatically turns on during automatic startup. If the CPU determines that the heater switch is ON but the temperature is not rising, an error message is displayed and the switch automatically turns OFF.
  • Page 68   □ Is the wiring in contact with other wiring or panels? Check the electrical circuits. □ Is the IS CTRL-A temperature control circuit functioning correctly? See section 4.7 IS CTRL-A Assy.
  • Page 69: Error Displayed After Filament Turns On

      Problems during tuning 10. Error displayed after filament turns on Display shows (090D) Trap/Total Current Low or (0D9C) Trap/Total Current Low. □ Are the filaments mounted correctly? Both filaments must be mounted correctly. □ Do the PC settings match the actual ion source installed? □...
  • Page 70: Details Of Electrical Circuits

      4. Details of Electrical Circuits Wiring Diagrams 1. Wiring diagram (Overall) 2. Wiring diagram (MAIN POWER ASSY) 3. Wiring diagram (Details) Unit Operation Checks 4. MAIN POWER ASSY 5. DC POWER-A 6. PCB ASSY, MAIN CTRL-A 7. IS CTRL-A ASSY 8.
  • Page 71: Wiring Diagram (Overall)

      Wiring Diagrams 1. Wiring diagram (Overall) Wiring Diagrams...
  • Page 72: Wiring Diagram (Main Power Assy)

      Wiring Diagrams 2. Wiring diagram (MAIN POWER ASSY)
  • Page 73: Wiring Diagram (Details)

      Unit Operation Checks 3.Wiring diagram (Details)
  • Page 74: Main Power Assy

      Unit Operation Checks 4. MAIN POWER ASSY Outline The MAIN POWER ASSY uses switching power supplies to convert the supply voltage (100 to 240VAC) into the various supply voltages: DC POWER-A (±24V), IG CTRL-A (+5V), and IS CTRL-A (+5V). It incorporates a PCB that provides ON/OFF control of the rotary pumps and turbo molecular pumps.
  • Page 75 GCMS-QP2010. Measure the AC voltage across L and N of the RP1 outlet at the rear of the GCMS-QP2010 to confirm that the voltage is 0V. Then, turn on RP1 and again measure the voltage across L and N of the RP1 outlet to confirm that it is equal to the instrument supply voltage.
  • Page 76   MAIN POWER ASSY Block Diagram...
  • Page 77: Dc Power-A

      Unit Operation Checks 5. DC POWER-A Outline DC POWER-A generates DC voltages for supply to CPU-A, PRE AMP-A, MAIN CTRL-A, IS CTRL-A, RF GENE-A and DI CTRL-A. Operation Check Method If an abnormality occurs, follow the procedures below to check the operation of the DC POWER-A PCB to efficiently diagnose the problem.
  • Page 78   voltage check. If the output voltages are still not normal, the DC POWER PCB is probably defective. Replace the DC POWER PCB. Conversely, if the voltages become correct after the connectors are disconnected, the problem is probably in the cable supplying the voltage or in the PCB receiving the voltage supply.
  • Page 79   DC POWER-A Block Diagram...
  • Page 80: Pcb Assy, Main Ctrl-A

      Unit Operation Checks 6. PCB ASSY, MAIN CTRL-A Outline MAIN CTRL-A generates the lens voltages, controls the solenoid valves, controls the high-voltage supply, measures the vacuum with the Pirani gauge, and provides voltage amplification functions for vacuum measurement using IG. It also functions as a relay board between CPU-A and IS CTRL-A and DI CTRL-A.
  • Page 81   If the output voltages differ from the set voltages, check if the D/A voltages supplied from the CPU PCB are correct. CP23 = set voltage/1.5 CP26 = set voltage/5 CP24 = set voltage/1.5 CP25 = set voltage/5 Abnormal D/A voltages suggest a defective CPU PCB. If the D/A voltages are normal but the output voltages are incorrect, conduct the following checks to determine if the problem is caused by an abnormality in the lens voltage generation circuits or by an abnormality in the vacuum vessel.
  • Page 82   should be 1 x conversion dynode setting (kV). Any abnormality in this voltage is probably due to incorrect D/A voltage from the CPU PCB. Check that when CD HV is ON, V ; when CD HV is OFF, V ≒...
  • Page 83   4. Checking the Pirani gauge measurement control circuits Check the operational amplifier power supply voltage. CP9 +5V Confirm that circuit output voltage is in the correct range. CP8 0.47 to 2.84V (1 to 300Pa) (Voltage decreases as the pressure increases.) CP8 0.07V max.
  • Page 84   MAIN CTRL-A Block Diagram...
  • Page 85  ...
  • Page 86: Is Ctrl-A Assy

      Unit Operation Checks 7. IS CTRL-A ASSY Outline IS CTRL-A provides functions for filament control and ion-source temperature control. It also functions as a relay board to introduce the lens voltages sent from MAIN CTRL-A into the vacuum vessel. Filament control (EI mode) If one filament is selected, the other filament can be used as a trap electrode.
  • Page 87   Set the lens voltages with the Peak Monitor and confirm the output voltages at the feedthrough contacts on the IS CTRL-A PCB. The normal output voltage lies in the range: set voltage ±5%. LENS1, LENS2, LENS3, LENS4 If the output voltages do not lie within the set ranges, conduct the checks described in 2. Checking the lens voltages for MAIN CTRL-A (page 60).
  • Page 88   Any abnormality suggests an incorrect D/A voltage from the CPU PCB. = set voltage (V) CP18 A voltage in the range set voltage ±10% is normal. If abnormal, check the voltage V CP19 If V is not in the range +1 to +15V, the IS CTRL PCB is probably defective. CP19 ≠set voltage, the filament wiring is If the V...
  • Page 89   The temperature sensor is a platinum (Pt) sensor. Check the voltage at CP8[TEMP]. ≥4V suggests a discontinuity in the platinum sensor or its wiring. ≒0V suggests a short-circuit in the platinum sensor or its wiring. The resistance of the platinum sensor varies approximately linearly from 100 to 250Ω in the temperature range from 0 to 400 C.
  • Page 90   IS-CTRL-A Block Diagram...
  • Page 91: Hv Pcb Assy

      Unit Operation Checks 8. HV PCB ASSY Outline HV PCB ASSY have the function that produces the high voltage of detection. MAIN CTRL-A have the function that controls the voltage and on/off that occur. HV PCB ASSY are being fixed inch a normal device, that is ,EI mode. HV PCB ASSY, NCI(225-11195-92 ) are being fixed in a NCI option.
  • Page 92   exchange this part. Please confirm the following, at the time of such that an electric discharge is occurring in a vacuum vessel. Please suspend a device. You had better confirm whether dust is not adhering, whether or not wiring is appropriate after takes out a detection device unit. There is case that is not determined as an error in the electric discharge of a weak electric discharge and period absence.
  • Page 93   Conversion dinode voltage   Measurement point: J12 [CD] Inside resistance: 33M Ω Detection device lens voltage   Measurement point: Field through Electrode Detection device lens voltage=0.084×conversion dinode voltage Conversion dinode voltage, becomes big 220V each to every measure current 1uA. When some extent is exceeded、...
  • Page 94   HV PCB ASSY block diagram (1) UNNCI case of model (EI,CI) (2) NCI case of model (NCI)
  • Page 95: Pcb Assy, Ig Ctrl-A

      Unit Operation Checks 9. PCB ASSY, IG CTRL-A Outline IG CTRL-A lights the ion-gauge measurement bulb (IG bulb) filament and generates the grid voltages. The MAIN CTRL-A PCB offers the functions to measure the collector current to determine the degree of vacuum. When the filament lights, thermoelectrons are discharged toward a grid held at a potential of +150V, resulting in a current from the grid to the filament (grid current).
  • Page 96   2. Checking the voltages Measure the voltage with the tester + probe on CP1[F+5VIG] and the - probe on CP2[F0VIG]. The normal voltage range when IG is off is +4.9 to +5.3V. The voltage drops slightly when IG turns on.
  • Page 97   3. Checking the grid and filament voltages Turn IG on with the tool program and measure the grid and filament voltages (CP4[GRID], CP5[FIL-], CP3[FIL+]). These voltages can also be measured at the IC bulb connector. Check the grid. Voltage across CP4[GRID] and IG bulb, Pin 4 = 15010±V Pull out the IG connector if V is abnormal.
  • Page 98   IG CTRL-A PCB Block Diagram...
  • Page 99: Pcb Assy, Cpu-A

    Turn on the PC, select Start, Settings, Control Panel to open the Control Panel. Select System and then click the Hardware tab and the Device Manager button. Confirm that GCMS-QP2010 is listed, as shown below. If GCMS-QP2010 appears correctly, check that the tool software runs.
  • Page 100   Explanation CPU-A incorporates the functions below. Function Description Comments DRAM E2PROM Temperature sensor IEEE1394 1 port For PC communications EIA232 1 port For GC communications 10Bit 8CH Built into CPU For data acquisition 16Bit 1CH Integrator FPGA 12Bit 12CH 16Bit 1CH For RF settings It is almost certain that CPU, DRAM, and IEEE1394 are operating correctly if the device...
  • Page 101   drivers are installed. Similarly, the E2PROM is probably operating correctly if the turbo molecular pump accumulated time is correctly calculated. EIA232 is operating correctly if GC communications are conducted normally. ADC and DAC operation can be confirmed on PCBs besides CPU-A. Checking the DIP switches CPU-A has two sets of DIP switches.
  • Page 102: Rf Ps Assy

      Unit Operation Checks 11. RF PS ASSY Outline The RF PS ASSY generates the high frequencies applied to the main rod and pre-rod. As shown in the block diagram, the main rod comprises a pair of opposing poles maintained at the same potential, to which the following voltages are applied: A pole = high-frequency (V) + DC voltage (U) + AC voltage (AC) + bias voltage B pole = high-frequency (-V) + DC voltage (-U) + AC voltage (-AC) + bias voltage...
  • Page 103   CP6 -24V (normal range: -22.7 to -25.3VDC) CP7 +24V (normal range: +22.7 to +25.3VDC) CP12 +5V (normal range: +4.8 to +5.3VDC)
  • Page 104   2. Checking the tuning Use the tool software to check if the tuning is correct. If tuning is correct (if the screen value valley can be confirmed by turning the core trimmer) it is safe to judge that the circuits related to the RF power-supply high frequency (V) are normal.
  • Page 105   If the checks above are all satisfactory but still no peaks are obtained, possibly the settings of trimmers VR1 and VR2 are seriously wrong. In this case, turn VR1 while monitoring the low mass numbers m/z18 and m/z28 to obtain equal peak amplitudes. If this adjustment is not possible even by fully turning VR1, switch JP1 and attempt the adjustment again.
  • Page 106   5. Checking the AC voltage The AC voltage is normal if 2 to 3V is output from CP15[AC] when m/z500 is set. (It fluctuates due to AC adjustment.) 6. Checking the pre-rod bias The pre-rod bias is normal if JT1[PRE] is within pre-rod bias set value ±10%. RF GENE-A Block Diagram M4(2/2) CP8[RF]...
  • Page 107: Pcb Assy,Di Ctrl-A

      Unit Operation Checks 12. PCB ASSY,DI CTRL-A Outline DI CTRL-A has the next function. There is a illumination of amplification and, LED of the heat electromotive force of heater voltage occurrence and, TC of DI probe and it is the function such as the recognition of a DI option furthermore.
  • Page 108   According to PWM of Duty in comparison to 0〜100%, 0 voltage,〜+24V comes out. 3.Confirmation of a TC temperature measurement circuit It is the voltage amplifier of 200 times. CP1[TMP-DI]: Voltage ≒ 0.008×(measurement temperature ℃-23) it becomes. ( 0.8V at the time of123℃...
  • Page 109   DI CTRL-A block diagram...
  • Page 110: Relay Box-A

      Unit Operation Checks 13. RELAY BOX-A Outline On/off of rotary pump 2 (RP2) that uses it with DI option in RELAY BOX-A is conducted. The relay point of contact signal is sent to the RP2 CTRL connector of the device back. On/off of RP2 is controlled in accordance with the on/off.
  • Page 111   the cause of an overcurrent is removed. 4.Confirmation of the inside The wiring and tab terminal inside RELAY BOX confirm whether they are not coming off. RELAY BOX-A block diagram...
  • Page 112: Appendices

      5. Appendices 1. Precautions during maintenance work 2. Adjustment in the high mass-number range 3. Detailed explanation of CI and NCI 4. Installation Guidelines (including List of Service Parts and Consumables) 5. Installation Completion Checksheet                         6. How to change Turbopump...
  • Page 113   1. Precautions during maintenance work Replacing CPU-A □ Restore the backed up E2PROM contents. □ Upgrade the Flash ROM, if required. Replacing RF PS Assy □ Sensitive to static electricity. Take care. □ Conduct tuning. □ Adjust according to the RF power supply adjustment. Replacing a turbo molecular pump (TMP) □...
  • Page 114   2. Adjustment in the high mass-number range This instrument incorporates an auto-tuning function that conducts mass-number calibration at m/z614. Mass-number displacement is rare in the normal range of operation (up to approximately m/z700.) However, displacement from the calibration at m/z is possible in the high mass-number range.
  • Page 115   Degree of residue After driving the triazine out of the column for one hour at 250 C, SCAN data measurements (approx. 1ppm) can be conducted without hindrance. Aging for 2 to 3 hours at 250 C is recommended for microanalysis (SIM measurement 100ppb or below) but aging overnight is recommended for ultramicroanalysis (10ppb or below).
  • Page 116: Detailed Explanation Of Ci And Nci

    GCMSsolution Ver. Order this system package together 225-06628-92 system package with GCMS-QP2010 main frame. Ver. 2.1 of the GCMSsolution is required to use the CI, NCI, and DI option. Major different points from 5050A EI and CI (SEI, SCI) can be simulated using the NCI ion source (for the NCI equipped model only) Simulated CI (SCI) mode in NCI ion source is added.
  • Page 117   [2] NCI 100fg octafluoronaphthalene 1. Sensitivity Molecular ion S/N>100 at M/Z272 (RMS) Reagent gas: methane, Scan range: 200-300u, Interval: 0.5sec Methane, isobutane, ammonia 2. Reagent gas Ion source box exchange type. Simulated EI (SEI*) and 3. Ion source simulated CI (SCI*) spectra can be collected using the NCI ion source box.
  • Page 118   Change from EI model Interface The interface for CI/NCI is different from that for EI, because reagent gas is introduced through interface in QP2010. Reagent gas controller Resistance tube 1 Reagent gas CI controller TW300 TW70 A 2 Reagent gas E2M1.5 RP Evacuation line of reagent gas...
  • Page 119   High voltage power supply for NCI Relay FOR EI and CI FOR EI and CI and NCI High voltage board High voltage board for detecting for NCI; both positive positive ions & negative voltages...
  • Page 120: Shimadzu Gas Chromatograph Mass Spectrometer

      4.Shimadzu Gas Chromatograph Mass Spectrometer GCMS-QP2010 Installation Guidelines (Installation Preparations and Checks) Analytical Instruments Division SHIMADZU CORPORATION...
  • Page 121 Please follow these guidelines to ensure safety, reliable analysis, and long use of the instrument. 2. Installation example The diagram on the next page shows the example of a standard GCMS-QP2010 configuration installed on a table. (The oil rotary pump is located on the floor.)
  • Page 122 ZEBV-5020C Installation example (The dimensions of the PC and printer may vary according to the model.) See below for the cable and pipe lengths. MS to rotary pump vacuum pipe approx. 1.5m power cable approx. 1.5m PC to MS cable approx.
  • Page 123 ZEBV-5020C single-phase 1000VA 2.5m Fig. 2 Separate power supplies are needed for the PC, monitor, and printer. 230V instrument Unit Voltage Capacity Cable length Terminal type 230VAC, 2600VA 2.0m Fig. 1 single-phase (*) 100VAC, 1000VA 2.5m Fig. 2 single-phase Separate power supplies are needed for the PC, monitor, and printer. Attention In the case that DI of a option is used the power supply of RP2 is necessary.
  • Page 124 ZEBV-5020C (*) Use a step-up transformer from a 100V or 200V amplifier. The maximum current with a 100VAC power supply is approximately 26A (with no options). Ensure the wiring has sufficient capacity. Use of the following step-up transformers is recommended. Cable Terminal Cat.
  • Page 125 5. Gas Helium (He) is employed as the carrier gas in the GCMS-QP2010. The gas type, purity, and pressure are designated in the table below. Provide gas and a gas pressure regulator of the types designated in the table, or their equivalents.
  • Page 126 See the List of Service Parts and Consumables for details. He gas purification filter kit GLC Center number: 544-102 Piping between cylinder and GC-QP2010 The following carrier gas pipes are available from Shimadzu. Order the pipe required before installing the instrument. Cat. No. Description...
  • Page 127 ZEBV-5020C Cautions on handling high-pressure gas cylinders The gas cylinders used are covered by the High-pressure Gas Safety Law. Strictly follow the provisions of the High-pressure Gas Safety Law when handling these cylinders. General Precautions 1. Locate the cylinders in a well-ventilated position outside that is not subjected to direct sunlight.
  • Page 128 Rotary pump 1 Exhaust Duct Example 7. Other parts to be prepared A Shimadzu service technician will adjust the instrument and measure inspection data immediately after the instrument is installed. Please have the following required items available at this time.
  • Page 129 ZEBV-5020C 8. Preparation checklist The checklist on the following pages summarizes the installation conditions described above. The customer is requested to complete this checklist and forward it to Shimadzu. Customer: Address: Telephone:...
  • Page 130 Confirmed Item Condition 1-1 Temperature Guaranteed within specification 18 to 28 C (constant) Installation Guaranteed operation 15 to 35 C room 1-2 Humidity 40% to 70% 1-3 Installation location Space 2000mm (W) x 700mm (D) Strength Able to support weight GC/MS unit approx.
  • Page 131 4. Exhaust 4-1 Exhaust duct plant for rotary pump Exhaust duct plant exhaust gases required. (Approx. 3 to /min.) 4-2 Oil-mist filter EMF3 042-00124-31 Required situations (option) where provision of an exhaust duct possible. 5. Others The following parts are required: 5-1 Capillary column DB-5ms (example J&W) L 30m I.D 0.25 Film 0.25um...
  • Page 132 List of Service Parts and Consumables (for replacement by customer) Replacement Description Comment Class frequency (guideline) 221-35507-02 SUPELCO SEPTUM (set of 50) 50 units/year (#1) Consumable 036-11203-84 FLUORORUBBER O-RING 20 units/year (#2) Consumable 221-41444-01 GLASS INSERT (FOR SPLIT) As required Consumable 221-48335-01 GLASS INSERT (FOR SPLITLESS MODE)
  • Page 133 200-33168 Seal Teflon As required Consumable 036-15550-12 Oring,AS568A-012 4D As required Consumable 225-09344 Sample vacuum bottle As required Consumable 225-04209 As required Consumable 225-10627-91 DI PROBE ASSY As required Consumable 225-10618-91 REPELLER2,CI+(C) IN DI mode ,CI analysis As required Consumable 225-09493-03 STANDARD SAMPLE (PFTBA) 5g As required...
  • Page 134 List of Service Parts and Consumables (for replacement by service technicians) Description Comment Replacement Class frequency (guideline) 221-46260-91 KEY OPERATION UNIT (PCB) Service part 078-12130-01 KEY OPERATION UNIT (LCD) Service part 221-46470 KEY OPERATION UNIT KEY RUBBER 1 (UPPER) Service part 221-46471 KEY OPERATION UNIT KEY RUBBER 2 (LOWER) Service part...
  • Page 135 225-10466-94 CDD CABLE ASSY, DET Service part 036-11271 O-RING, 4D P105 Service part 225-10464-91 FEEDTHROUGH ASSY, CDD Service part 225-09148-92 FEEDTHROUGH Service part 036-11218 O-RING, 4DP18 Service part MS FILTER 225-01132 TERMINAL PINS Service part 225-10407-91 CABLE ASSY, MS FILTER Service part 225-10408-91 SHORT CABLE 1, PRE-ROD...
  • Page 136 225-09517-01 RP E2M1.5(100-200) No cable Overhaul every 1.5 Service part years (#3) 225-09517-02 RP E2M1.5(220-240) No cable Overhaul every 1.5 Service part years (#3) 225-11446-91 CABLE, MS-RP RP cable Service part 221-09895-09 LABEL, AC220 240V Label for cable Service part 221-09895-10 LABEL, AC110 115V Label for cable...
  • Page 137 225-11075-91 RF PS ASSY Service part RF PS 225-11060-91 PCB ASSY, RF DIFF-A Service part 225-10296-91 FAN ASSY Service part MAIN CTRL 225-11130-91 PCB ASSY, MAIN CTRL-A Service part CPU PCB 225-11000-91 PCB ASSY, CPU-A Service part IS CTRL 225-11225-91 IS CTRL-A ASSY Service part DC POWER...
  • Page 138: Installation Completion Checksheet

    ZEAV-0416A 5.Installation Completion Checksheet Shimadzu Gas Chromatograph Mass Spectrometer GCMS-QP2010 Name: Department: User's name: I have checked the items in the attached checklist and report that the installation is complete. Installation completion date: Installation supervisor: Department: Model name Serial number...
  • Page 139 ZEAV-0416A Shimadzu Corporation 2010 Installation Completion Checklist The items relate to acquiring installation completion data and conducting operation checks. Installation is complete when all items in the installation completion checklist have been checked and the operation instruction completed. (A standard installation requires four working days.) Analysis of the customer's samples is separate from the installation process.
  • Page 140 ZEAV-0416A □ b. Mass spectra * Take and keep mass spectrometer (MS) and Normal operation measurement mass chromatogram (MC) sensitivity s (MS, MC) measurement data from practical operation. Measurement conditions shown below. (This checks the operation of the MS and MC software.) c.
  • Page 141 ZEAV-0416A Measure S/N.(EI MODE and NCI MODE) EI SAMPLE OFN 1pg/ul (isookutane solvent) 1ul m/z272 S/N≧60 NCI SAMPLE OFN 0.1pg/ul(100fg/ul)( isookutane solvent) 1ul  m/z272 S/N≧100 Measurement Conditions 250 C SPLITLESS mode (sampling time 1.0 minute) COL: 50 C (1min) - 40 C / min - 200 C (0min) - 15 C / min - 280 C I/F: 250 C 200 C...
  • Page 142: How To Change Turbopump

    6. How to change Turbopump Replacement Procedure of Turbomolecular Pump ~ QP2010 ~ TW300 1. Shut down QP2010 and turn off the power. Remove capillary column from interface and separate MS part from GC part more than 20cm. Disconnect the control cable for interface temperature. If MS part cannot be kept enough distance from GC part, move MS part to another work table after disconnecting all the cable from MS part.
  • Page 143 3. Remove the front cover. Remove Loosen the Loosen the screws at the both the screw. screw sides of cover. Remove Loosen the the screw. screw Remove the screw. Remove the screw. Remove the front door. Remove the cover. - 119 -...
  • Page 144 4. Remove the right side panel. The above work can be easily done by previously removing the connector for interface heater. (The connector can be easily removed by clipping its both side with your fingers) - 120 -...
  • Page 145 5. Remove the IS CTRL-A Board Unit. Disconnect the two connectors. Remove the three screws and the spacer screw - 121 -...
  • Page 146 Disconnect the feedthrough connection, indicated by arrow, by holding the IS CTRL-A board in both hands. ( Be careful not to put insufficiently strong power into the feedthrough) Put wires aside and remove the IS CTRL-A board unit. - 122 -...
  • Page 147 Disconnect the connector from the power supply for TW300, which is the rear one of the two power supplies for turbomolecular pump. (After removing the cable) - 123 -...
  • Page 148 7.Remove the outlet flange of TW300. Loosen three screws. Slide the presser plate to the arrowhead to remove it. Remove the flange and the o-ring. (Be careful to avoid dust) - 124 -...
  • Page 149 Remove TW300. Put cardboard between the TW300 main body and the power unit. (This procedure will make the later work easier.) Loosen gradually the diagonal 4 fixing screws. (Do not remove the screws at this step.) The front-left side screw can be loosened by putting the wrench into clearance, as shown in the picture.
  • Page 150 Do not remove the 2 screws on the right side. Remove the 2 screws on the left side. - 126 -...
  • Page 151 Remove cardboard. Move the TW300 left by holding in both hands. - 127 -...
  • Page 152 Take out the TW300 by supporting securely its bottom side and its inlet part. Be careful not to hit and broke the IG gauge, indicated by arrow. (Work with clean hands. We recommend you to wear clean gloves.) Completion of removal - 128 -...
  • Page 153 Replacing the power unit. Loosen the fixing screw, indicated by arrow. Disconnect the two connectors. Loosen the fixing screw and slide the presser plate to remove the power unit. Install the new power unit, TURBO DRIVE 300. The 'REMOTE' terminal will be used. Do not use the 'SERVICE' terminal.
  • Page 154 Preparation of new TW300 New TW 300 Removed TW300 Check the name plate. Old type                                          New type - 130 -...
  • Page 155 Remove the cap of outlet. Loosen the 3 fixing screws and remove the plate Remove the o-ring. - 131 -...
  • Page 156 Remove the o-ring and the protective net from the removed TW300 for reuse. You can remove the protective net by hooking it with tweezers. (We recommend wear clean gloves.) If it is difficult for you to remove the protective net, try to hook the fringe of it.
  • Page 157 Installing the new TW300         Place the protective net and the o-ring in the new TW300. Make sure that there is no dust on sealing surface, o-ring and protective net. Make sure that there are no dust and no scratches on sealing surface of vacuum manifold Put cardboard on the power unit of turbomoecular pump.
  • Page 158 Hook the right side hooks on the neck of inlet. Attach the left side screws and hooks. Fasten lightly the 4 screws. - 134 -...
  • Page 159 Adjust the mounting angle to be rotated, as shown in figure. Make sure that the edge of the bottom side does not protrude. Tighten step by step opposite pair of 4 screws in turn. - 135 -...
  • Page 160 Remove the cardboard. Completion of TMP mounting - 136 -...
  • Page 161 12. Fix the flange to outlet Place the flange on the outlet. (Do not forget to place o-ring) - 137 -...
  • Page 162 13. Reinstallation of IS CTRL-A Board unit Push the feedthrough into the connector on IS CTRL-A board. This work can be easily done if you put the metal plate for fixing on the vacuum manifold and slide horizontally the board unit. (Be careful not to put insufficiently strong power into the feedthrough.) Make sure that all pins of feed-through are stuck into the connector holes of IS CTRL-A board.
  • Page 163 Slide fast the IS CTRL-A board down and fix it. (4 screws) Connect the two connectors. - 139 -...
  • Page 164 14. Place the covers.     Place the front cover. Place the front door. - 140 -...
  • Page 165   Replace the power unit box and the top cover. Connect the control cable for interface temperature. Make sure that there is no vacuum leak by plugging interface and starting instrument before connecting GC and MS. Reset the operating time of turbomolecular pump as the following procedure. - 141 -...
  • Page 166 Resetting the operating time of turbomolecular pump Execute the software “MS2010.exe”. (This software is stored in C:¥GCMSSolution¥PROGRAM¥MS2010.) Enter password. : ******** The following screen will be opened. Select “Tools” from the toolbar menu. Click “E2PROM”. - 142 -...
  • Page 167   The above screen will be opened. Write down the value of TMP1 Time in the working report. UPDATE EDIT CLOSE MODE Select “Edit mode”. - 143 -...
  • Page 168 UPDATE SET”0” TMP1 Time if if TMP1 has been replaced with the new one. Click the button “Update”. CANSEL Click “OK” to close the window. The operating time of TMP1 has been reset. Write down the serial numbers of the troubled TMP and the new TMP in the working report. Start up the instrument.

Table of Contents

Save PDF