Download Print this page
Panduit PANVIEW iQ PVQ-MIQPS96F Installation Instructions
Panduit PANVIEW iQ PVQ-MIQPS96F Installation Instructions

Panduit PANVIEW iQ PVQ-MIQPS96F Installation Instructions

Modular intelligent panel system

Advertisement

Quick Links

© Panduit Corp. 2008
(4) P
V
AN
(16) U
ID
(16) Grounded Bonding
LTIMATE
Label Covers
1.
While PViQ Patch Panels work interchangeably with either
the Panel Manager (PM) or the Expansion Module (EM), it is
recommended that PViQ Patch Panels be placed in a manner
that will efficiently accommodate one (1) PM for every three
(3) EMs, with appropriate cable management installed for
proper cable routing. NOTE: PM can be arranged at either
the top or bottom of order depending on need or preference.
Module Installation
3.
With the PViQ Patch Panel secured to the rack or cabinet, proceed to
install terminated jack modules into the patch panel (as shown above).
NOTE: The PViQ Patch Panel accepts all M
Modules and LC Fiber Adapters.
For Technical Support: www.panduit.com/resources/install_maintain.asp
INSTALLATION INSTRUCTIONS
iQ Patch Panels
IEW
(4) Mounting Brackets for
Screws
P
V
AN
IEW
Rack Mounting and Grounding
PM Installation
EM Installation
Cable
Management
EM Installation
EM Installation
-C
Copper Jack
INI
OM
P
V
AN
IEW
Intelligent Panel System
Part Number: PVQ-MIQPS96F
Hardware Components
(1) Panel
Manager (PM)
(1) Patch Cord
iQ Modules
2.
Install screws
in 4 places
Use ONLY supplied grounding screws
Mount the PViQ Patch Panel onto the face of
the rack or rack cabinet using supplied
grounding screws (as shown).
PViQ Patch Panels MUST be properly
grounded to ensure accurate system
operation.
It is advisable to prepare cable management by routing cables into a
left/right and upper/lower separation as you install the terminated jack
modules (as shown above) to reserve appropriate space for the
addition of mounting bracket later.
Page 1 of 3
iQ (PViQ) Modular
PN467
(1) PM Interface
(3) Expansion
Unit
Modules (EM)
(3) Expansion Port Cables
provide appropriate
grounding, the following
S
Kits from PANDUIT are
recommended:
(Recommended) Cable Routing
Leave room for
Mounting Bracket
(3) EM Interface
Units
If supplied screws
do not fit or work
with your rack or
rack cabinet to
G
Rack
TRUCTURED
ROUND
• Grounding Strip Kit
(Part # RGS134-1Y)
• ESD Port Kit
(Part # RGESD2-1)
• CBN Network Jumper Kit
(Part # RGCBNJ660P22)

Advertisement

loading
Need help?

Need help?

Do you have a question about the PANVIEW iQ PVQ-MIQPS96F and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for Panduit PANVIEW iQ PVQ-MIQPS96F

  • Page 1 (PViQ) Modular Intelligent Panel System Part Number: PVQ-MIQPS96F INSTALLATION INSTRUCTIONS PN467 © Panduit Corp. 2008 Hardware Components (4) P iQ Patch Panels (1) Panel (1) PM Interface (3) Expansion (3) EM Interface Manager (PM) Unit Modules (EM) Units (16) U...
  • Page 2 PMs to the LAN (either port may be used for connecting to LAN or subsequent PMs); c.) 12VDC power input supplied by power supply (PANDUIT Part# PVQ-PS12VDC-*, sold separately). EM Connections - The EM module includes expansion ports which are used to connect the EMs to the PM or subsequent EMs. d.) The "Out" port connects to downstream EMs.
  • Page 3 (Refer to table above for label products) WARNINGS: If a non-PANDUIT power source is used, it must: • Provide over current protection appropriate to the size of the power wiring connected to the PViQ System. • Provide an isolated (SELV) source per National requirements.