4.
Step 2 Secure the power cables to the tower vertically using cable clips.
Step 3 Remove the cable ties, PVC insulation tape, and lifting sling.
----End
Issue 07 (2013-12-30)
Figure 6-11 Wrapping the PVC insulation tape
Installation engineer C pulls the lifting sling downwards, and installation engineer B pulls
the other end of the lifting sling outwards to protect the power cables from colliding with
the tower.
NOTE
The procedure for hoisting the power cables onto the tower is for your reference only.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.