Service Interval Summary Table - Carrier 50CJ Installation, Operation And Maintenance Instructions

Table of Contents

Advertisement

Available languages
  • EN

Available languages

  • ENGLISH, page 41

10 - SERVICE INTERVAL SUMMARY TABLE

Regular maintenance will keep the unit running at optimum performance levels. The values given in the table below are provided for 
guidance only. They do not take into account individual factors that can lengthen or shorten the unit's service life.
COMPONENT
Filters
Cooling coil
Electric heater (option)
Humidifier (option)
(1)
Fans
Electrics box
Hydraulic circuit
Water leak detection sensor
and relay
Filter pressure switch
Thermostat and fire control relay
Valve 
CL2 condensation unit
(1)  If a water softener or water treatment system is used, the water hardness should not be less than 40 % of the initial hardness and should never be less than 15 °F.
AT COMMISSIONING
- Check the connections 
- Check the connections
- Check the connections
- Check the connections
- Check correct operation
- Check correct operation and 
setpoint adjustment
- Check correct operation
- Check circuit for correct operation 
and tightness
2-3 MONTHS
- Replace
- Clean
- Clean
- Check the condition of the 
cylinder, replacing it if necessary 
- Check correct operation
- Check correct operation and 
setpoint adjustment
- Check correct operation
Refer to the corresponding instructions
12 MONTHS
- Replace
- Check and clean the condensate 
drains
- Retighten the electrical 
connections
- Check the components
- Retighten the electrical 
connections
- Check the components
- Check the condensate drains
- Make sure that steam is evenly 
distributed
- Retighten the electrical 
connections
- Retighten the electrical 
connections
- Check the components
- Check the components
- Check the insulation
- Check correct operation
- Check correct operation and 
setpoint adjustment
- Check correct operation
- Check correct operation
63

Advertisement

Table of Contents
loading

Table of Contents