Connecting The Internal Dc Power Supply To The Dc Source Voltage; Grounding A Summit Dc-Powered Switch - Extreme Networks Summit X450a-24tDC Hardware Installation Manual

Extremexos summit family switches summit x150 series summit x250e series summit x350 series summit x450 series summit x450a series summit x450e series
Hide thumbs Also See for Summit X450a-24tDC:
Table of Contents

Advertisement

NOTE
For centralized DC power connection, these products are intended to be installed in Restricted Access Locations
(Dedicated Equipment Rooms, Equipment Closets, or the like) in accordance with Articles 110-16, 110-17, and
110-18 of the National Electric Code, ANSI/NFPA 70.
NOTE
An optional redundant power supply, the EPS-150DC, is available for use with the Summit DC-powered switches.
When the EPS-150DC is used with a DC-powered Summit switch, the power supplies (internal and redundant) are
fully fault tolerant and load-sharing. If one power supply fails, the other power supply will provide sufficient power to
operate the switch. Refer to
Connecting the Internal DC Power Supply to the DC Source
Voltage
Before you connect the switch to a power source, complete the physical installation of the switch in the
equipment rack, as described in
If you are installing a Summit DC-powered switch, you must ground the chassis before connecting the
switch to the DC source voltage (see

Grounding a Summit DC-Powered Switch

Before you connect the power input cable to a Summit DC-powered switch, you must ground the
chassis, following the instructions in this section.
Gather the following materials to ground the Summit DC-powered switch:
Stranded copper wire cable, minimum size 14 AWG, maximum size 6 AWG
The wire should be long enough to reach from the installed switch to the facility ground point
Torque screwdriver with 1/4-inch flat blade
Additional grounding hardware appropriate to the earth ground connection at your site
WARNING!
Be sure to connect the chassis ground wire before you connect any power cables.
To ground the switch:
1 At one end of the wire, strip the insulation to expose 1/2 inch (12 mm) of bare wire.
2 Identify the grounding lug on the back of the switch. The grounding lug is next to the edge of the
back panel, identified by the international symbol for earth ground. Depending on the switch model,
the grounding lug may be on either side (see
Summit Family Switches Hardware Installation Guide
"EPS-150DC External Power Module (with EPS-T2)" on page 58
"Rack-Mounting a Summit Switch" on page
"Grounding a Summit DC-Powered Switch"
Figure
Installing and Removing Summit DC-Powered Switches
85.
57).
for further details.
below).
87