Installing The Control Station 1 Outer Slide Rails; Installing Components; Installation Order Of System Components - EMC VNX Series Installation Manual

Hide thumbs Also See for VNX Series:
Table of Contents

Advertisement

Assemble components in your cabinet

Installing the Control Station 1 outer slide rails

Installing components

Installation order of system components

28
EMC VNX Series VNX5600 Unified Installation Guide
Figure 11 Installing stabilizer screws
The Control Station 1 outer slide rails are installed directly above the Control Station 0
rails.
Procedure
1. Locate the Control Station 1 outer slide rails previously removed from the shipping
rack.
2. Repeat the installation procedure described in
slide rails on page 24
CAUTION
Some of the components are heavy and lifting and attaching them to the rack may
require two people. If needed, use an appropriate lifting device (mechanical lift).
Install the components in the appropriate order.
Install your VNX system components in the following order:
CAUTION
Components are not interchangeable. Ensure that you install the components in the
following order. Otherwise, your storage system will not operate properly.
1. Disk processor enclosure
2. Blade enclosure 0
3. (optional) Blade enclosure 1
4. Control Station 0
to install Control Station 1.
CL4854
Installing the Control Station 0 outer

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Vnx5600

Table of Contents